Project management : Set up reporting tool (MS Project & MS Excel)

Presented by Jan Biets

Jan_biets@hotmail.com      +32(0)477   32   90   11             Mechelen          -   Belgium
                                                 page 1 • reporting (graphical)
Reporting, analysing, steering [PDCA] : result driven pm

                                                         project progress : mandays                                                                            project progress : budget [€] & mandays

                                                                                                                                        250                                                                          10
                          10
                                                                                                                                                                                                  baseline [€]
                                                                                                                                        200                                                       actual [€]
                                                                                                                                                                                                  baseline budget
                                                                                                                                        150                                                       baseline [md]
                                                                                                                                                                                                  actuals [md]
                                                                                                                                                                                                                     5
                 %




                           5                                                                                                                                                                      reserved budget
                                                                                                                                        100


                                                                                                                                        50


                                                                                                                                         0                                                                           0
                           0                                                                                                                  1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
                                1 2 3        4   5   6    7   8   9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
                       baseline (abs)                                                                                                                                   reporting cycle
                                                                      reporting cycle
                       actual (abs)                                                                                                           project progress : mandays                   (cumulative)
                                                              Deliverables Chart
                                                                                                                             100
                       sep/11
                                                                                                                              90
                         jul/11                                                                                               80
  Deliverables dates




                        jun/11                                                                                                70
                                                                                                                              60
                        apr/11
                                                                                            Business Requirements
                                                                                                                      %


                                                                                                                              50
                                                                                            Functional Design
                        feb/11                                                                                                40
                                                                                            Coding & Testing
                                                                                            Launch                            30
                        jan/11
                                                                                                                              20
                        nov/10
                                                                                                                              10
                                  baseline               28/02/2011        31/03/2011      30/04/2011           31/05/2011
                                                                      reporting cycle                                          0
                                                                                                                                    1 2       3 4   5 6    7   8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
                                                                                                                             baseline
                                                                                                                                                                        reporting cycle
                                                                                                                             actual

Project management Dynamics                                                                                                           December 2012




                                                                                                                                                                                                                          BVBA
Project management : set up tracking &
  reporting tool (MS Excel)
   Once, the WBS is finalised (baseline), open ‘VIEW’ / ‘Tracking Gantt’ .




Project management Dynamics              December 2012




                                                                             BVBA
Project management : set up tracking &
  reporting (MS Excel)
   Set view on ‘Resource usage’




Project management Dynamics       December 2012




                                                  BVBA
• Select timescale granularity (cursor on timescale/right mouse click / select Middle Tier ‘month’, and
       Bottom Tier ‘week’
     • Select all dat and copy (use control-c)




Project management Dynamics                                December 2012




                                                                                                               BVBA
Open MS Excel (new file)
     Paste the copied selections (hours)
     Select all, and find&replace ‘h’ door ‘ ‘




Project management Dynamics                 December 2012




                                                            BVBA
Cross check the sum of all cells, with ‘total work’ in MS Project file
   add tracking period (reporting period / frequency) on upper row (e.g.:
   wk 1 , wk 2, wk 3,…)
   Totalise planned hours per resource , or group
   Add the resource names (e.g. : name 1 , name 2 , name 3,…)
   You can now start to develop your own reporting & tracking tool

resource   totaal     wk 1      wk 2      wk 3      wk 4      wk 5      wk 6      wk 7      wk 8      wk 9      wk 10     wk 11     wk 12     wk 13     wk 14     wk 15     wk 16     wk 17     wk 18     wk 19     wk 20     wk 21     wk 22     wk 23     wk 24     wk
naam 1          978,2      26,7      44,5      26,7      44,5      25,6        32        32        41        36        32        32      19,2                  32        32                  32        32        32        32                  32        32        32
naam 2           1160                                                32        40        40        40        40        40        40        32        40        40        40        32        40        40        40        40        40        40        40        40
naam 3            977                                                                                                                                                    40        32        79        48        53        26     34,97     49,03        36        40
naam 4            624                            24         6                                               4,8                                   22,15     17,85        43      51,2        64        64        31        26        61        60         2
naam 5            600                                                                                                  16                  16        20        20        20        16        20        20        20     45,25      59,5     33,25        16        40
naam 6        1120,21        40      27,2                                                                                        32        46       122                  62         0        40        26                  17        40        40        40     45,22
naam 7         991,15        54                0,93      0,45      0,37      0,45      0,45      2,88      28,5      34,5      61,5      79,4         0                          80,4      52,5      38,9      10,5      10,5      50,5      50,5      90,5     47,72
naam 8          719,2         0                 0,2                                                          16        63                  32        44                                      17      35,1      12,9        44        21         2     39,02    109,73
naam 9          485,2                           0,2                                                                    24        40        64        54        40         3                  24        40        40        26
naam 10           851      65,5                                                                                                  16        41        28        10                            40        40        40        40        30                  24       174
naam 11            40         0
naam 12        621,02                            24        40        32         8                7,75        10        10        39        53                                      68     38,23     22,72     48,13     75,47      23,7      22,4     16,47     17,67
naam 13        107,99                         12,48      20,8     16,63      20,8      20,8     16,48                                                                                                                                                     0
naam 14         444,5                                                                             1,3      1,67      1,67      1,67      1,33      1,67      1,67                                    1,67      1,67     21,07     25,67     35,67     45,67     25,67
naam 15         33,34         8                                                                     0         0         0         0         0                             0         0         0                   0         5         0      0,97      1,67      1,67
naam 16        699,72                                                                                                7,82      7,82      6,25      7,82      7,82      7,82      6,25      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82
naam 17        446,11                                                                                                7,82      7,82      6,25      7,82      7,82      7,82      6,25      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82
naam 18        355,12                                                                                                7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82
naam 19        235,12        24        30         6                                                                  7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82      7,82
naam 20           270                                                                                                                                                                                                                                    50        20
naam 21             0
naam 22           800                                                                                                  40        40        40        40        40        40        40        40        40        40        40        40        40        40        40
naam 23           374                                                32        40        40        40        40        40        40        40        40        22
naam 24             0
naam 25             0
naam 26             0
naam 27        691,09                                                32        40        40        40        40     47,82     47,82     47,82     47,82     47,82     47,82     46,82     23,82     71,82     15,82     39,82      7,82      6,25
naam 28             0
naam 29             0         0
naam 30             0
naam 31             0
naam 32           483                                                                                                   8         8         8         8         8         8         8         8         8         8         8         8         8         8         8
naam 33            30                                                                                                                                                                                                                                    30
naam 34            72        72
naam 35           432
naam 36            40
naam 37           162                                                31                                                                                                                       8        40        15        40        28




Project management Dynamics                                                                                                           December 2012




                                                                                                                                                                                                                                                        BVBA
Reporting, analysing, steering [PDCA] : result driven pm

                                                         project progress : mandays                                                                            project progress : budget [€] & mandays

                                                                                                                                        250                                                                          10
                          10
                                                                                                                                                                                                  baseline [€]
                                                                                                                                        200                                                       actual [€]
                                                                                                                                                                                                  baseline budget
                                                                                                                                        150                                                       baseline [md]
                                                                                                                                                                                                  actuals [md]
                                                                                                                                                                                                                     5
                 %




                           5                                                                                                                                                                      reserved budget
                                                                                                                                        100


                                                                                                                                        50


                                                                                                                                         0                                                                           0
                           0                                                                                                                  1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
                                1 2 3        4   5   6    7   8   9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
                       baseline (abs)                                                                                                                                   reporting cycle
                                                                      reporting cycle
                       actual (abs)                                                                                                           project progress : mandays                   (cumulative)
                                                              Deliverables Chart
                                                                                                                             100
                       sep/11
                                                                                                                              90
                         jul/11                                                                                               80
  Deliverables dates




                        jun/11                                                                                                70
                                                                                                                              60
                        apr/11
                                                                                            Business Requirements
                                                                                                                      %


                                                                                                                              50
                                                                                            Functional Design
                        feb/11                                                                                                40
                                                                                            Coding & Testing
                                                                                            Launch                            30
                        jan/11
                                                                                                                              20
                        nov/10
                                                                                                                              10
                                  baseline               28/02/2011        31/03/2011      30/04/2011           31/05/2011
                                                                      reporting cycle                                          0
                                                                                                                                    1 2       3 4   5 6    7   8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
                                                                                                                             baseline
                                                                                                                                                                        reporting cycle
                                                                                                                             actual

Project management Dynamics                                                                                                           December 2012




                                                                                                                                                                                                                          BVBA
Set up of reporting & progress tracking tool (MS Project –
     MS Excel)

      • As of this point, you are able to develop further to a complete tracking and
        reporting tool, upon your own needs.


      • More explanation about this tool, you will find at: www.slideshare/jan biets
        / graphical view on reporting




Project management Dynamics                    December 2012




                                                                                       BVBA

More Related Content

PDF
Q2 presentation
PDF
Q4 presentation
PPTX
Meta evaluation presentation 010611secondpresentation
PDF
2008* Embraer Day ApresentaçãO AviaçãO Executiva
PDF
Obama FY2010 Budget
PDF
CCM Performance March 2012
PDF
SEB Chevreux Conference Stockholm March 2009
Q2 presentation
Q4 presentation
Meta evaluation presentation 010611secondpresentation
2008* Embraer Day ApresentaçãO AviaçãO Executiva
Obama FY2010 Budget
CCM Performance March 2012
SEB Chevreux Conference Stockholm March 2009

What's hot (6)

PDF
Natan Gavish - Welcome to the Cloud 2
PDF
Wilson Euec 2010
PDF
AREVA, 2008 annual results
PPTX
Coffee and cocoa suitability map.
XLS
2010 Budget Department DRAFT Budget
PDF
Attention flow by tagging prediction
Natan Gavish - Welcome to the Cloud 2
Wilson Euec 2010
AREVA, 2008 annual results
Coffee and cocoa suitability map.
2010 Budget Department DRAFT Budget
Attention flow by tagging prediction
Ad

More from Jan Biets [[email protected]] (16)

PPTX
PPTX
CIP eu 2016 114(-8)
PPTX
PPTX
Blockchain private permissioned
PPT
PPT
Project Management Flight stimulator 1.0
PPT
Project planning logic, how to optimise your schedule
PPT
PPT
Graphical project reporting-v1-0
PPTX
Project management dynamics
PPT
trusted archiving authority - LTANS
CIP eu 2016 114(-8)
Blockchain private permissioned
Project Management Flight stimulator 1.0
Project planning logic, how to optimise your schedule
Graphical project reporting-v1-0
Project management dynamics
trusted archiving authority - LTANS
Ad

Recently uploaded (20)

PPTX
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
PPTX
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
PDF
Kishore Vora - Best CFO in India to watch in 2025.pdf
DOCX
Handbook of entrepreneurship- Chapter 7- Types of business organisations
DOCX
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
DOCX
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
PDF
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
PPTX
CTG - Business Update 2Q2025 & 6M2025.pptx
PPTX
df0ee68f89e1a869be4bff9b80a7 business 79f0.pptx
PDF
Sustainable Digital Finance in Asia_FINAL_22.pdf
PDF
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
PDF
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
PDF
Chapter 2 - AI chatbots and prompt engineering.pdf
PPTX
IITM - FINAL Option - 01 - 12.08.25.pptx
PDF
HQ #118 / 'Building Resilience While Climbing the Event Mountain
PPTX
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
PPTX
IMM marketing mix of four ps give fjcb jjb
PDF
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
PDF
Comments on Clouds that Assimilate Parts I&II.pdf
PDF
Middle East's Most Impactful Business Leaders to Follow in 2025
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
Kishore Vora - Best CFO in India to watch in 2025.pdf
Handbook of entrepreneurship- Chapter 7- Types of business organisations
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
CTG - Business Update 2Q2025 & 6M2025.pptx
df0ee68f89e1a869be4bff9b80a7 business 79f0.pptx
Sustainable Digital Finance in Asia_FINAL_22.pdf
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
Chapter 2 - AI chatbots and prompt engineering.pdf
IITM - FINAL Option - 01 - 12.08.25.pptx
HQ #118 / 'Building Resilience While Climbing the Event Mountain
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
IMM marketing mix of four ps give fjcb jjb
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
Comments on Clouds that Assimilate Parts I&II.pdf
Middle East's Most Impactful Business Leaders to Follow in 2025

Set up pm reporting & tracking tool

  • 1. 03-23-05 December 2012 BVBA Project management : Set up reporting tool (MS Project & MS Excel) Presented by Jan Biets [email protected] +32(0)477 32 90 11 Mechelen - Belgium page 1 • reporting (graphical)
  • 2. Reporting, analysing, steering [PDCA] : result driven pm project progress : mandays project progress : budget [€] & mandays 250 10 10 baseline [€] 200 actual [€] baseline budget 150 baseline [md] actuals [md] 5 % 5 reserved budget 100 50 0 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 baseline (abs) reporting cycle reporting cycle actual (abs) project progress : mandays (cumulative) Deliverables Chart 100 sep/11 90 jul/11 80 Deliverables dates jun/11 70 60 apr/11 Business Requirements % 50 Functional Design feb/11 40 Coding & Testing Launch 30 jan/11 20 nov/10 10 baseline 28/02/2011 31/03/2011 30/04/2011 31/05/2011 reporting cycle 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 baseline reporting cycle actual Project management Dynamics December 2012 BVBA
  • 3. Project management : set up tracking & reporting tool (MS Excel) Once, the WBS is finalised (baseline), open ‘VIEW’ / ‘Tracking Gantt’ . Project management Dynamics December 2012 BVBA
  • 4. Project management : set up tracking & reporting (MS Excel) Set view on ‘Resource usage’ Project management Dynamics December 2012 BVBA
  • 5. • Select timescale granularity (cursor on timescale/right mouse click / select Middle Tier ‘month’, and Bottom Tier ‘week’ • Select all dat and copy (use control-c) Project management Dynamics December 2012 BVBA
  • 6. Open MS Excel (new file) Paste the copied selections (hours) Select all, and find&replace ‘h’ door ‘ ‘ Project management Dynamics December 2012 BVBA
  • 7. Cross check the sum of all cells, with ‘total work’ in MS Project file add tracking period (reporting period / frequency) on upper row (e.g.: wk 1 , wk 2, wk 3,…) Totalise planned hours per resource , or group Add the resource names (e.g. : name 1 , name 2 , name 3,…) You can now start to develop your own reporting & tracking tool resource totaal wk 1 wk 2 wk 3 wk 4 wk 5 wk 6 wk 7 wk 8 wk 9 wk 10 wk 11 wk 12 wk 13 wk 14 wk 15 wk 16 wk 17 wk 18 wk 19 wk 20 wk 21 wk 22 wk 23 wk 24 wk naam 1 978,2 26,7 44,5 26,7 44,5 25,6 32 32 41 36 32 32 19,2 32 32 32 32 32 32 32 32 32 naam 2 1160 32 40 40 40 40 40 40 32 40 40 40 32 40 40 40 40 40 40 40 40 naam 3 977 40 32 79 48 53 26 34,97 49,03 36 40 naam 4 624 24 6 4,8 22,15 17,85 43 51,2 64 64 31 26 61 60 2 naam 5 600 16 16 20 20 20 16 20 20 20 45,25 59,5 33,25 16 40 naam 6 1120,21 40 27,2 32 46 122 62 0 40 26 17 40 40 40 45,22 naam 7 991,15 54 0,93 0,45 0,37 0,45 0,45 2,88 28,5 34,5 61,5 79,4 0 80,4 52,5 38,9 10,5 10,5 50,5 50,5 90,5 47,72 naam 8 719,2 0 0,2 16 63 32 44 17 35,1 12,9 44 21 2 39,02 109,73 naam 9 485,2 0,2 24 40 64 54 40 3 24 40 40 26 naam 10 851 65,5 16 41 28 10 40 40 40 40 30 24 174 naam 11 40 0 naam 12 621,02 24 40 32 8 7,75 10 10 39 53 68 38,23 22,72 48,13 75,47 23,7 22,4 16,47 17,67 naam 13 107,99 12,48 20,8 16,63 20,8 20,8 16,48 0 naam 14 444,5 1,3 1,67 1,67 1,67 1,33 1,67 1,67 1,67 1,67 21,07 25,67 35,67 45,67 25,67 naam 15 33,34 8 0 0 0 0 0 0 0 0 0 5 0 0,97 1,67 1,67 naam 16 699,72 7,82 7,82 6,25 7,82 7,82 7,82 6,25 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 naam 17 446,11 7,82 7,82 6,25 7,82 7,82 7,82 6,25 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 naam 18 355,12 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 naam 19 235,12 24 30 6 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 naam 20 270 50 20 naam 21 0 naam 22 800 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 naam 23 374 32 40 40 40 40 40 40 40 40 22 naam 24 0 naam 25 0 naam 26 0 naam 27 691,09 32 40 40 40 40 47,82 47,82 47,82 47,82 47,82 47,82 46,82 23,82 71,82 15,82 39,82 7,82 6,25 naam 28 0 naam 29 0 0 naam 30 0 naam 31 0 naam 32 483 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 naam 33 30 30 naam 34 72 72 naam 35 432 naam 36 40 naam 37 162 31 8 40 15 40 28 Project management Dynamics December 2012 BVBA
  • 8. Reporting, analysing, steering [PDCA] : result driven pm project progress : mandays project progress : budget [€] & mandays 250 10 10 baseline [€] 200 actual [€] baseline budget 150 baseline [md] actuals [md] 5 % 5 reserved budget 100 50 0 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 baseline (abs) reporting cycle reporting cycle actual (abs) project progress : mandays (cumulative) Deliverables Chart 100 sep/11 90 jul/11 80 Deliverables dates jun/11 70 60 apr/11 Business Requirements % 50 Functional Design feb/11 40 Coding & Testing Launch 30 jan/11 20 nov/10 10 baseline 28/02/2011 31/03/2011 30/04/2011 31/05/2011 reporting cycle 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 baseline reporting cycle actual Project management Dynamics December 2012 BVBA
  • 9. Set up of reporting & progress tracking tool (MS Project – MS Excel) • As of this point, you are able to develop further to a complete tracking and reporting tool, upon your own needs. • More explanation about this tool, you will find at: www.slideshare/jan biets / graphical view on reporting Project management Dynamics December 2012 BVBA