2
Most read
5
Most read
6
Most read
SPM-UNIT III
RISK MANAGEMENT
Prof. Kanchana Devi
PERT Technique
 Used to evaluate the effects of uncertainty
 CPM & PERT are similar
 CPM requires Single Estimate
 PERT requires Three Estimates
2
Prof. Kanchana Devi
PERT Three Estimates are
Prof. Kanchana Devi
3
 Most Likely Time
 The time we would expect the task to take under
normal circumstances.“ m”
 Optimistic Time
 Shortest time in which we could expect to complete
the activity, barring the miracles.“a”
 Pessimistic Time
 Worst Possible time. “b”
Expected Duration
Prof. Kanchana Devi
4
 PERT Combines the three estimates to form a
single expected duration, te
 Formula for te is
te= a+4m+b
6
Calculate the expected duration
Prof. Kanchana Devi
5
Activity Optimistic(a) Most Likely(m)
Activity Duration
Pessimistic(b)
A 5 6 8
B 3 4 5
C 2 3 3
D 3.5 4 5
E 1 3 4
F 8 10 15
G 2 3 4
H 2 2 2.5
After Calculating Expected
Duration
Prof. Kanchana Devi
6
PERT Network after the
Prof. Kanchana Devi
7
Activity Standard Deviation
Prof. Kanchana Devi
8
 S = b-a which gives the degree of uncertainty
6
 The activity standard deviation is proportional to
the difference between the optimistic and
pessimistic estimates.
 Can be used as a ranking measure of the degree of
uncertainty or risk for each activity
Standard Deviation
Prof. Kanchana Devi
9
PERT With ‘SD’
Prof. Kanchana Devi
10
Probability of Meeting or Missing
Target Date
Prof. Kanchana Devi
11
 The PERT Technique uses the following three
step method for calculating the probability
of meeting or missing a target date:
 Calculate SD of each project event
 Calculate the Z value for each event that has a target
value
 Convert Z values to a probability
Prof. Kanchana Devi
12
 Note: To add two Standard Deviations we
must add their squares and then find the
square root of the sum.
 The SD for event 3 depends on the activity B.
The SD for event 3 is therefore 0.33
 For event 5 there are two possible paths, B+E
or F. The total SD for path B+E is
√(0.332+0.502) = 0.6 and For path F is 1.17
 SD for event 5 is therefore the greater of two
1.17
Z- Value Formula
Prof. Kanchana Devi
13
 Te  is the Expected Date
 T  Target Date
 S  SD
Z = T - te
S
Calculate Z value –Event ‘4’
Prof. Kanchana Devi
14
 (10-9.00)/0.53 = 1.8867
 A Z-Value may be converted to the
probability of not meeting the target date by
using the graph given below
Converting Z values to
Probabilities
Prof. Kanchana Devi
15
 A Z-value may be converted to the
probability of not meeting the target date by
using the graph.
 Eg:
 The Z-Value for the project completion (event 6)
is 1.23. Using graph this equates to a probability
of approximately 11%, that is, there is an 11%
risk of not meeting the target date of the end of
week 15.
Monte Carlo Simulation
Prof. Kanchana Devi
16
 An alternative to PERT Technique
 MC Simulation are a class of general analysis
techniques that are valuable to solve any
problem that is complex, nonlinear or for some
uncertain parameters.
 It involves repeated random sampling to
compute the results.
 Advantage:
 Repeated computation of random numbers - easier
to use this technique when available as a computer
program
Steps – MC Simulation
Prof. Kanchana Devi
17
 Step 1: Express the project completion time in terms of the
duration of the n-activities xi,i=1,n and their dependencies
as a precedence graph, d= f(x1,x2,….xn).
 Step 2: Generate a set of random inputs, Xi1,Xi2, …Xin using
the specified probability distributions.
 Step 3: Evaluate the project completion time expression
and store the result in di.
 Step 4: Repeat steps 2 and 3 for the specified number of
times.
 Step 5: Analyze the results di, i=1,n; summarize and display
using a histogram.
Histogram
Prof. Kanchana Devi
18

More Related Content

PPTX
File handling in c++
DOCX
Software Engineering Assignment
PPTX
Software Project Management
PDF
Problem solving methodology
PDF
Algorithm and c language
PPT
BackTracking Algorithm: Technique and Examples
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PPTX
Modular programming
File handling in c++
Software Engineering Assignment
Software Project Management
Problem solving methodology
Algorithm and c language
BackTracking Algorithm: Technique and Examples
MG6088 SOFTWARE PROJECT MANAGEMENT
Modular programming

What's hot (20)

PPTX
System Programming Unit III
PPT
Project Management Control
PPTX
Spm unit iii-risk-intro
PPTX
SPM Activity Planning Introduction
PPT
Spm unit 4
PPTX
COCOMO MODEL 1 And 2
PPTX
SPM Evaluation
PPT
Software estimation
PPTX
Halsted’s Software Science-An analytical technique
PPT
Factors for Successful Projects
PPTX
Unit1 principle of programming language
PPT
Overview of project planning
PPT
Software effort estimation
PDF
Software Project Management (SPM)
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PPTX
RMMM Plan
PPT
software-project-management-unit-2.ppt
PPTX
Software Project Management
PPT
C by balaguruswami - e.balagurusamy
System Programming Unit III
Project Management Control
Spm unit iii-risk-intro
SPM Activity Planning Introduction
Spm unit 4
COCOMO MODEL 1 And 2
SPM Evaluation
Software estimation
Halsted’s Software Science-An analytical technique
Factors for Successful Projects
Unit1 principle of programming language
Overview of project planning
Software effort estimation
Software Project Management (SPM)
MG6088 SOFTWARE PROJECT MANAGEMENT
RMMM Plan
software-project-management-unit-2.ppt
Software Project Management
C by balaguruswami - e.balagurusamy
Ad

Viewers also liked (7)

PPTX
Spm unit iii-risk-resource allocation
PPT
Spm unit 3
PPTX
Spm unit iii-risk-working in teams
PPT
List of 10 Sales Performance Management (SPM) Vendors
PPTX
Spm unit iii-risk-monitoring & control1
PPT
Spm unit 1
PPSX
Leadership In Project Management
Spm unit iii-risk-resource allocation
Spm unit 3
Spm unit iii-risk-working in teams
List of 10 Sales Performance Management (SPM) Vendors
Spm unit iii-risk-monitoring & control1
Spm unit 1
Leadership In Project Management
Ad

Similar to Spm unit iii-risk-pert (20)

PPTX
Applying the PERT Technique_UNIT III.pptx
PPTX
Project Scheduling techniques in Project PERT.pptx
PPT
PPTX
Lec 10 pert estimating techniques
PPTX
Pert and cpm
PPTX
PPTX
Establishing schedule margin using monte carlo simulation
PDF
PPTX
udjjjmmmmkxkkkskllklkakk,z,,,skkdmmxjd.pptx
PDF
Cpm module iii reference
PPT
CHAPTER 4 THE PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT).ppt
PPTX
Quantitative analysis for business decision- Program Evaluation and Review Te...
PPTX
Ch 06 - CPM PERT (1).pptx
PPTX
Using Risk Analysis and Simulation in Project Management
PPTX
Lecture 5 Project Scheduling-PERT.pptx
PPTX
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
PPTX
Seminar on pert
PPT
PDF
Pert techniques
Applying the PERT Technique_UNIT III.pptx
Project Scheduling techniques in Project PERT.pptx
Lec 10 pert estimating techniques
Pert and cpm
Establishing schedule margin using monte carlo simulation
udjjjmmmmkxkkkskllklkakk,z,,,skkdmmxjd.pptx
Cpm module iii reference
CHAPTER 4 THE PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT).ppt
Quantitative analysis for business decision- Program Evaluation and Review Te...
Ch 06 - CPM PERT (1).pptx
Using Risk Analysis and Simulation in Project Management
Lecture 5 Project Scheduling-PERT.pptx
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
Seminar on pert
Pert techniques

More from Kanchana Devi (9)

PPTX
Spm unit v-software reliability-
PPTX
Spm unit v-software maintenance-intro
PDF
Spm unit iii-configuration mgmt-responsibilities
PPTX
Spm unit iii-configuration mgmt-intro
PDF
Spm ap-network model-
PDF
Spm software effort estimation
PDF
Spm project planning
PPTX
Open source spm tools
PPTX
Software project management introduction
Spm unit v-software reliability-
Spm unit v-software maintenance-intro
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-intro
Spm ap-network model-
Spm software effort estimation
Spm project planning
Open source spm tools
Software project management introduction

Recently uploaded (20)

PDF
Principles of operation, construction, theory, advantages and disadvantages, ...
PPTX
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
PDF
Beginners-Guide-to-Artificial-Intelligence.pdf
PPTX
Environmental studies, Moudle 3-Environmental Pollution.pptx
PPTX
Software-Development-Life-Cycle-SDLC.pptx
DOCX
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
PDF
Using Technology to Foster Innovative Teaching Practices (www.kiu.ac.ug)
PDF
Artificial Intelligence_ Basics .Artificial Intelligence_ Basics .
PDF
MLpara ingenieira CIVIL, meca Y AMBIENTAL
PDF
Research on ultrasonic sensor for TTU.pdf
PPTX
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
PDF
[jvmmeetup] next-gen integration with apache camel and quarkus.pdf
PDF
ASPEN PLUS USER GUIDE - PROCESS SIMULATIONS
PDF
Software defined netwoks is useful to learn NFV and virtual Lans
PDF
VTU IOT LAB MANUAL (BCS701) Computer science and Engineering
PPTX
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
PPTX
AI-Reporting for Emerging Technologies(BS Computer Engineering)
PPTX
WN UNIT-II CH4_MKaruna_BapatlaEngineeringCollege.pptx
PPTX
Unit IImachinemachinetoolopeartions.pptx
PPTX
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
Principles of operation, construction, theory, advantages and disadvantages, ...
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
Beginners-Guide-to-Artificial-Intelligence.pdf
Environmental studies, Moudle 3-Environmental Pollution.pptx
Software-Development-Life-Cycle-SDLC.pptx
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
Using Technology to Foster Innovative Teaching Practices (www.kiu.ac.ug)
Artificial Intelligence_ Basics .Artificial Intelligence_ Basics .
MLpara ingenieira CIVIL, meca Y AMBIENTAL
Research on ultrasonic sensor for TTU.pdf
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
[jvmmeetup] next-gen integration with apache camel and quarkus.pdf
ASPEN PLUS USER GUIDE - PROCESS SIMULATIONS
Software defined netwoks is useful to learn NFV and virtual Lans
VTU IOT LAB MANUAL (BCS701) Computer science and Engineering
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
AI-Reporting for Emerging Technologies(BS Computer Engineering)
WN UNIT-II CH4_MKaruna_BapatlaEngineeringCollege.pptx
Unit IImachinemachinetoolopeartions.pptx
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS

Spm unit iii-risk-pert

  • 2. PERT Technique  Used to evaluate the effects of uncertainty  CPM & PERT are similar  CPM requires Single Estimate  PERT requires Three Estimates 2 Prof. Kanchana Devi
  • 3. PERT Three Estimates are Prof. Kanchana Devi 3  Most Likely Time  The time we would expect the task to take under normal circumstances.“ m”  Optimistic Time  Shortest time in which we could expect to complete the activity, barring the miracles.“a”  Pessimistic Time  Worst Possible time. “b”
  • 4. Expected Duration Prof. Kanchana Devi 4  PERT Combines the three estimates to form a single expected duration, te  Formula for te is te= a+4m+b 6
  • 5. Calculate the expected duration Prof. Kanchana Devi 5 Activity Optimistic(a) Most Likely(m) Activity Duration Pessimistic(b) A 5 6 8 B 3 4 5 C 2 3 3 D 3.5 4 5 E 1 3 4 F 8 10 15 G 2 3 4 H 2 2 2.5
  • 7. PERT Network after the Prof. Kanchana Devi 7
  • 8. Activity Standard Deviation Prof. Kanchana Devi 8  S = b-a which gives the degree of uncertainty 6  The activity standard deviation is proportional to the difference between the optimistic and pessimistic estimates.  Can be used as a ranking measure of the degree of uncertainty or risk for each activity
  • 10. PERT With ‘SD’ Prof. Kanchana Devi 10
  • 11. Probability of Meeting or Missing Target Date Prof. Kanchana Devi 11  The PERT Technique uses the following three step method for calculating the probability of meeting or missing a target date:  Calculate SD of each project event  Calculate the Z value for each event that has a target value  Convert Z values to a probability
  • 12. Prof. Kanchana Devi 12  Note: To add two Standard Deviations we must add their squares and then find the square root of the sum.  The SD for event 3 depends on the activity B. The SD for event 3 is therefore 0.33  For event 5 there are two possible paths, B+E or F. The total SD for path B+E is √(0.332+0.502) = 0.6 and For path F is 1.17  SD for event 5 is therefore the greater of two 1.17
  • 13. Z- Value Formula Prof. Kanchana Devi 13  Te  is the Expected Date  T  Target Date  S  SD Z = T - te S
  • 14. Calculate Z value –Event ‘4’ Prof. Kanchana Devi 14  (10-9.00)/0.53 = 1.8867  A Z-Value may be converted to the probability of not meeting the target date by using the graph given below
  • 15. Converting Z values to Probabilities Prof. Kanchana Devi 15  A Z-value may be converted to the probability of not meeting the target date by using the graph.  Eg:  The Z-Value for the project completion (event 6) is 1.23. Using graph this equates to a probability of approximately 11%, that is, there is an 11% risk of not meeting the target date of the end of week 15.
  • 16. Monte Carlo Simulation Prof. Kanchana Devi 16  An alternative to PERT Technique  MC Simulation are a class of general analysis techniques that are valuable to solve any problem that is complex, nonlinear or for some uncertain parameters.  It involves repeated random sampling to compute the results.  Advantage:  Repeated computation of random numbers - easier to use this technique when available as a computer program
  • 17. Steps – MC Simulation Prof. Kanchana Devi 17  Step 1: Express the project completion time in terms of the duration of the n-activities xi,i=1,n and their dependencies as a precedence graph, d= f(x1,x2,….xn).  Step 2: Generate a set of random inputs, Xi1,Xi2, …Xin using the specified probability distributions.  Step 3: Evaluate the project completion time expression and store the result in di.  Step 4: Repeat steps 2 and 3 for the specified number of times.  Step 5: Analyze the results di, i=1,n; summarize and display using a histogram.