Overall Equipment Effectiveness
TM
The Critical KPI to Drive
Manufacturing Productivity
2
TM
A net reduction in cost of operations directly and positively affects the bottom line. Companies can boost revenue
without sacrificing profitability by factoring in long-term debt-to-capital ratio. Since finance puts a premium on
a company’s ability to maximize productivity and use existing assets, you have to continually measure, analyze,
and adjust your processes. This is accomplished by a rigorous practice of productivity gains, cost cutting with
increased efficiencies, and maximizing returns on fixed assets.
Though complex, this productivity improvement affects labor, equipment, consumables, procedures, quality, and
capital investment.
As part of the plan to improve, the following goals are common for most manufacturers:
•	 Increase capacity / decrease time to produce
•	 Increase return on assets
•	 Reduce operating costs
•	 Better manage capital
•	 Increase total shareholder returns
How do you accomplish these goals?
An Introduction to OEE
A powerful method to improve manufacturing productivity
Overall Equipment Effectiveness (OEE) has emerged as a powerful method of evaluating the productivity of
production systems. This ebook will be a guide to OEE – so you can lead your Operational Excellence team.
3
TM
Definition of OEE
OEE is an effective methodology to help improve the
productivity of manufacturing processes. Since the
early 1990s, OEE has emerged as a leading approach for
accurately measuring true plant productivity.
Initially, OEE was regularly associated with Total
Productive Maintenance (TPM) programs. It is now being
looked at as a powerful means of evaluating the Key
Performance Indicators (KPIs).
By definition, OEE is the
product of Availability,
Performance, and Quality
category percentages:
Where:
Availability = Downtime Losses
Performance = Speed Losses
Quality = Defect Losses
OEE =
Availability * Performance * Quality
Total Productive Maintenance (TPM) is a maintenance system covering life of all equipment:
planning, manufacturing, and maintenance. Improving performance via elimination of the 6 major
types of waste. OEE is the formula for defining equipment effectiveness in a TPM program.
3
4
TM
OEE is made up of three categories:
Each one of these OEE components represents losses that result in a reduction of Production Time. We begin with
Total Available Time and subtract time losses due to Availability (Downtime), Performance (Speed), and Quality
(Reject/Rework). Very quickly, one can see the effects of these losses on production time.
Productive Time becomes a fraction of Total Available Time. By using and understanding the losses, you can take
the actions necessary to increase Productive Time as much as possible. Figure 1 illustrates the time losses due to
various OEE categories.
Understanding OEE Terminology
Figure 1 – Time Losses
*Planned Shutdown Time, or time when the productive capacity is not needed, is not normally
Total Available Time
Planned Production Time
Planned
Shutdown*
Operating Time Availability
Loss
Net Operating Time Performance
Losses
Productive Time Quality
Losses
}OEE
Availability
The ratio of the
Operating Time to the
Planned Production Time
Performance
The rate at which equipment
converts available time
into product. Calculation
excludes availability and
quality losses.
Quality
Percentage of parts which
meet specifications. OEE
recognizes quality as only
one aspect of equipment
utilization.
included in the OEE calculation.
5
TM
Total Available Time: This is the time the plant is open and could be used for production
(excluding holidays).
Planned Production Time: This is the Total Available Time minus the Planned Shutdown Time.
Planned Shutdown could include meal breaks, or scheduled maintenance; changeover is often
categorized as loss of Planned Production Time.
Operating Time: This is the difference between Planned Production Time and the time lost to
downtime. Downtime events include equipment breakdown, unscheduled maintenance, setup
time and changeover. This is included in the OEE calculations.
Net Operating Time: This is the difference between the Operating Time and time lost to Speed
reduction. Speed reduction events include operating equipment at below rated speed (increased
cycle time), frequent short-lived stoppages not requiring maintenance, and certain operator
errors. This is included in the OEE calculations.
Productive Time: This is the difference between the Net Operating Time and the time lost to
Quality issues. Quality losses include rejected and reworked products. This is included in the
OEE calculations. Figure 1 describes how each OEE Category is calculated.
5
6
TM
OEE Calculations
Downtime
Losses
Availability: The ratio of Operating Time to Planned
Production Time (Operating Time is Planned Production
Time Less Downtime Loss). Availability of 100% means the
process has been running with no stops.
Availability = Operating Time / Planned Production Time
Speed
Losses
Quality
Losses
Quality: The ratio of Good Parts to Total Parts. Quality of
100% means there have been no reject or rework parts.
Quality = Good Parts / Parts Produced
Performance: The ratio of Theoretical/Ideal Speed to Actual
Speed. Performance of 100% means the process has been
consistently running at its theoretical maximum speed.
Performance = Parts Produced / (Ideal Speed * Operating Time)
7
TM
Defining OEE Events
Within each OEE Category, there are several events that must be identified, correctly measured, and analyzed.
There are situations (or events) that may require further thought to decide to which category they belong. For
example, short-lived stops and operator errors could be recorded as either Availability (Downtime) or Performance
(Speed) losses. The correct categorization will be made based on the specific manufacturing process and plant. It
is important to be consistent and uniform in categorizing events in order to get reliable results.
As stated above, there are many events that affect OEE. By implementing an OEE practice, you can reduce these
commonly occurring loss events to increase the overall plant productivity. Figure 2 provides a list of the Common
Loss Events, and the attributed categories.
Common Events OEE Category Comment
Equipment Breakdowns Availability Loss Depending on the specifics of the production environment,
certain variety of breakdowns not requiring maintenance could be
categorized as Performance/Speed Losses
Process Setup and Adjustments Availability Loss Includes certain operator errors and product changeovers
Short Stops and Idling Performance Loss Short stops are typically those which do not require maintenance.
Generally, problems with consumables could be categorized as
Performance/Speed Losses
Reduced Speed Performance Loss Factors such as equipment age or production anomalies that keep
the operation from running at the maximum theoretical speed
would be included in this category
Startup Rejects Quality Loss Production loss (rejected) during initial stages (transition) of
startup prior to reaching steady state (regularly producing good
products)
Production Rejects Quality Loss Products lost (rejected due to defect) during the normal production
stages
Figure 2
8
TM
The purpose of implementing an OEE program is to improve productivity.
It is important to know what you are aiming to achieve. What is considered to be world-class OEE? Are the
components of OEE important by themselves? These are very significant questions.
By general consensus, world-class OEE is 85% or higher. By contrast, most manufacturing plants have an OEE
in the range of 30 – 60%. It is not unusual for these plants to experience daily fluctuations of about 10% - there
is room for improvement.
What is Considered World-Class OEE?
Availability
90%
Performance
95%x x
Quality
99.9%
Overall OEE
85%=
Components of World-Class OEE
9
TM
Achieving world-class OEE is quite challenging and requires the
need to consistently follow a rigorous program. This means regular
measurement, analysis, and taking action based on the findings.
An important point to keep in mind is that you must look at all four
numbers (OEE, Availability, Performance, and Quality) together and
individually. Though it may sound contradictory since OEE is a measure
of productivity, it is possible to have a reasonable OEE without having an
acceptable individual component score.
With each component of OEE being counted equally (A*P*Q), each needs
to be diligently inspected. Don’t forgo quality (more rejects or rework) to
increase output or performance. If the balance in achieving a higher OEE
is off, the outcome may be unacceptable.
Scrutinize each
component of OEE:
Quick tip
•	 Availability
•	 Performance
•	 Quality
•	 Overall OEE
A
PQ
P
AQ
Q
AP
10
TM
Benchmark OEE
In a recent survey conducted by LNS Research, nearly 200 companies across multiple disciplines reported
their OEE numbers. From these findings, it seems world-class OEE is being met in a number of factories –
especially in Life Sciences and Discrete – but just how far is this from reality?
From these ranges, the numbers seem to be significantly inflated compared to the reality of most
manufacturers. The OEE of these industries tend to be more shocking in practice. With the proper
methodology, technical ability, and infrastructure in place, you can achieve world-class manufacturing
numbers.
You cannot misrepresent the numbers if you plan to act on them. Get accurate, automated, real time insight
into your shop floor with TrakSYS™.
Let’s look at a real life example.
Highest Reported OEE Median OEE Lowest Reported OEE Average OEE Range
100
10
20
30
40
50
60
70
80
90
Batch
Manufacturing
94
75
58
Discrete
Manufacturing
99
85
50
Food & Beverage
/ CPG
95
78
55
Life
Sciences
98
85
45
Process
Manufacturing
94
80
72
11
TM
It is good to know what OEE and its components are but in order to have a good understanding of the
concept, it is helpful to look at a real example. Consider a beverage plant with the following production
schedule for the bottling area:
A Real Example
Figure 4 - Production Data for Calculation of OEE and its Components
Item Data
Days of Operation Planned 5
Number of Shifts 15 (3 per day, 8 hrs. each)
Total Planned Shutdown 2,400 minutes (160 minutes/shift)
Downtime 1,250 minutes (for all shifts)
Theoretical (Ideal) Rate 600 bpm (bottles per minute)
Total Bottles Produced 1,656,502
Rejected Bottles 1,207
12
TM
The Breakdown
Planned Production Time
Total Available Time – Total Planned Shutdown
Operating Time
Planned Production - Downtime
Good Bottles
Total Bottles - Rejected Bottles
7,200 - 2,400 = 4,800 minutes
4,800 - 1,250 = 3,550 minutes
1,656,502 - 1,207 = 1,655,295
Availability
Operating Time / Planned Production Time
Quality
Good Bottles / Total Bottles Produced
Performance
Bottles Produced / (Ideal Rate * Operating Time)
3,550 / 4,800 = 0.73 (or 73%)
1,655,295 / 1,656,502 = 0.99
(or 99%)
1,656,502 / ( 600 bpm * 3,550 )
= 0.7777 (or 77%)
Real-Time
Plant Data
Calculated
Metrics
OEE
Availability * Performance * Quality
0.73 * 0.77 * 0.99
= 0.57 (or 57%)
KPI
13
TM
13
Considering that OEE can also be defined as:
OEE = Productive Time / Planned Production Time
Then:
	 Productive Time = OEE * Planned Production Time
		 =	 0.5748 * 4,800 minutes
		 =	 2,759.04 minutes
Also, consider if downtimes and short-lived stoppages were reduced by 10% or 125
minutes, the same factory would be able to produce 58,327 more bottle during the same
five-day period (assuming the same effective performance). With the wholesale price of
each bottle at $0.85, during each five-day period, the bottling area can produce $49,578
more sellable product. If the bottling area is operating 260 days during the year, the extra
production will be worth $2,578,056 without extra shifts or overtime.
14
TM
Global competition dictates the need to optimize assets, labor, and processes, making Overall Equipment
Effectiveness (OEE) an essential KPI. Though important for continuous improvement, many companies
still struggle with collecting accurate OEE data and characterizing the root cause(s) behind variations in
productivity.
A manual process to collect OEE data, e.g. clipboards and whiteboards, is often inaccurate, delayed, and/or
involves extra paperwork and operator dependencies. The next improvement step is to implement software
capable of directly monitoring the control systems running the plant assets.
Web-based reports, automated alerts via email or text message, and web journals create a highly engaged
and responsive team for significant improvement. These results will tie directly to specific plant initiatives,
whether expanding capacity of the existing assets, reducing changeover times, reducing overtime, reducing
rework and scrap, or improving customer service levels.
Conclusion
To learn more, visit
pages.parsec-corp.com/productivity.html
or contact us
marketing@parsec-corp.com
15
TM
About Parsec
Parsec Automation Corp. (Parsec) is the developer of TrakSYS™, the leading real-time operations & performance
management software. Manufacturing companies worldwide rely on Parsec for flexible and configurable tools to
execute manufacturing operations across the value chain more effectively.
Without production disruption, TrakSYS™ helps manufacturers to significantly improve asset utilization and
efficiency, increase capacity with no new capital equipment, reduce production costs, decrease lead time, and
improve profitability. With measurable ROI, TrakSYS™ fuels Lean, Six Sigma, TPM, and Operational Excellence
efforts. For more information about Parsec, please visit the corporate Web site at www.parsec-corp.com.
© 2015

More Related Content

PDF
Operational-Excellence
PPSX
Quality awareness
PPTX
Cost of-poor-quality - juran institute
PPT
How to Introduce Operational Excellence in your Organisation?
PPT
Oee and its Application
PPTX
A New Perspective on Operational Excellence
PDF
Operational Excellence model
PDF
Overall Equipment Effectiveness
Operational-Excellence
Quality awareness
Cost of-poor-quality - juran institute
How to Introduce Operational Excellence in your Organisation?
Oee and its Application
A New Perspective on Operational Excellence
Operational Excellence model
Overall Equipment Effectiveness

What's hot (20)

PPTX
Awareness of iatf 16949
PPTX
Lean Manufacturing Tools
PPT
Identify 7 Wastes
PDF
Change Control Process PowerPoint Presentation Slides
PPTX
Daily Production Management - 5 Tips to Maintain Stability & Exclusion of Abn...
PPTX
Quality Awareness Session.pptx
PPTX
6 OEE overview
PPTX
Total productive maintenance(TPM)
PPTX
PPT Presentation on IATF 16949 Documentation
PPTX
FMEA Introduction.ppt
PPT
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
PDF
Operational Excellence Powerpoint Presentation Slides
PPTX
Spc training
PPTX
Training module 4 m change
PDF
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PDF
OEE-Presentation.pdf
PPTX
Achieving Operational Excellence - A better approach for a complex world
Awareness of iatf 16949
Lean Manufacturing Tools
Identify 7 Wastes
Change Control Process PowerPoint Presentation Slides
Daily Production Management - 5 Tips to Maintain Stability & Exclusion of Abn...
Quality Awareness Session.pptx
6 OEE overview
Total productive maintenance(TPM)
PPT Presentation on IATF 16949 Documentation
FMEA Introduction.ppt
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Operational Excellence Powerpoint Presentation Slides
Spc training
Training module 4 m change
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
OEE-Presentation.pdf
Achieving Operational Excellence - A better approach for a complex world
Ad

Viewers also liked (20)

PPTX
Design For OEE (DFOEE)
PPTX
OEE IMPLEMENTATION part 1
PDF
Oee on hana overall equipment effectiveness overview aug 2012 (2)
PPTX
Integrating OEE and Process Improvement
PDF
Oee guide
PDF
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
PPTX
KEY PERFORMANCE INDICATOR
PPT
Oee Explained
PDF
Electronic Batch Records
PPT
Project Management KPIs
PDF
Benefits of Collecting OEE Data with Production Tracking Software
PPTX
The Six Big Losses of OEE
PPT
KPI for HR Manager - Sample of KPIs for HR
PPT
Developing Metrics and KPI (Key Performance Indicators
PDF
CV - Ninett Vestergaard Madsen
PDF
Effective Management of Electronic Batch Records
PDF
Overall Equipment Effectiveness: A Strategic and Practical Improvement Tool
PDF
TrakSYS by Parsec
PDF
Crystal ball of Manufacturing
Design For OEE (DFOEE)
OEE IMPLEMENTATION part 1
Oee on hana overall equipment effectiveness overview aug 2012 (2)
Integrating OEE and Process Improvement
Oee guide
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
KEY PERFORMANCE INDICATOR
Oee Explained
Electronic Batch Records
Project Management KPIs
Benefits of Collecting OEE Data with Production Tracking Software
The Six Big Losses of OEE
KPI for HR Manager - Sample of KPIs for HR
Developing Metrics and KPI (Key Performance Indicators
CV - Ninett Vestergaard Madsen
Effective Management of Electronic Batch Records
Overall Equipment Effectiveness: A Strategic and Practical Improvement Tool
TrakSYS by Parsec
Crystal ball of Manufacturing
Ad

Similar to OEE - The Critical KPI to Drive Manufacturing Productivity (20)

PDF
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
PPTX
benefits from calculating overall equipment effectivness
PPTX
Overall Equipment Effectiveness (OEE).pptx
PDF
The+complete+guide+to+simple+oee
PDF
Overall equipment effectiveness of critical machines in manufacturing industries
PDF
Managing OEE o optimize factory performance
PPTX
Overall equipment effectiveness
PDF
OEE vs TEEP.pdf
PDF
A Manager's Guide to OEE (Overall Equipment Effectiveness)
PDF
Overall Equipment Effectiveness in Construction Equipments
PDF
OEE Fact sheet
PDF
How To Track OEE
PPTX
OEE (overall eqipment effectiveness)
PPTX
Overall Equipment Effectiveness, Complete Lecture.pptx
PPTX
oecawesfearegegrtgtgesfvtrhujhgfdewrdee.pptx
PDF
A038301010
PPTX
OEE.pptx
PDF
Why OEE?
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
benefits from calculating overall equipment effectivness
Overall Equipment Effectiveness (OEE).pptx
The+complete+guide+to+simple+oee
Overall equipment effectiveness of critical machines in manufacturing industries
Managing OEE o optimize factory performance
Overall equipment effectiveness
OEE vs TEEP.pdf
A Manager's Guide to OEE (Overall Equipment Effectiveness)
Overall Equipment Effectiveness in Construction Equipments
OEE Fact sheet
How To Track OEE
OEE (overall eqipment effectiveness)
Overall Equipment Effectiveness, Complete Lecture.pptx
oecawesfearegegrtgtgesfvtrhujhgfdewrdee.pptx
A038301010
OEE.pptx
Why OEE?

Recently uploaded (20)

PDF
El futuro en e sector empresarial 2024 e
PPTX
Biomass_Energy_PPT_FIN AL________________.pptx
PPTX
Enterprises are Classified into Two Categories
PDF
109422672-Doc-8973-05-Security-Manual-Seventh-Edition.pdf
PDF
From Legacy to Velocity: how we rebuilt everything in 8 months.
PDF
The Influence of Historical Figures on Legal Communication (www.kiu.ac.ug)
PDF
HQ #118 / 'Building Resilience While Climbing the Event Mountain
PDF
The Impact of Historical Events on Legal Communication Styles (www.kiu.ac.ug)
DOCX
“Strategic management process of a selected organization”.Nestle-docx.docx
PDF
El futuro empresarial 2024 una vista gen
DOCX
Handbook of entrepreneurship- Chapter 10 - Feasibility analysis by Subin K Mohan
PDF
France's Top 5 Promising EdTech Companies to Watch in 2025.pdf
PPTX
Cơ sở hạ tầng công nghệ thông tin trong thời đại kỹ thuật số
PDF
Nante Industrial Plug Socket Connector Sustainability Insights
PDF
Handouts for Housekeeping.pdfbababvsvvNnnh
PDF
Handouts for Housekeeping.pdfhsjsnvvbdjsnwb
PDF
757557697-CERTIKIT-ISO22301-Implementation-Guide-v6.pdf
DOCX
Center Enamel Enabling Precision and Sustainability in the Netherlands' Advan...
PDF
Pink Cute Simple Group Project Presentation.pdf
PPTX
Oracle Cloud Infrastructure Overview July 2020 v2_EN20200717.pptx
El futuro en e sector empresarial 2024 e
Biomass_Energy_PPT_FIN AL________________.pptx
Enterprises are Classified into Two Categories
109422672-Doc-8973-05-Security-Manual-Seventh-Edition.pdf
From Legacy to Velocity: how we rebuilt everything in 8 months.
The Influence of Historical Figures on Legal Communication (www.kiu.ac.ug)
HQ #118 / 'Building Resilience While Climbing the Event Mountain
The Impact of Historical Events on Legal Communication Styles (www.kiu.ac.ug)
“Strategic management process of a selected organization”.Nestle-docx.docx
El futuro empresarial 2024 una vista gen
Handbook of entrepreneurship- Chapter 10 - Feasibility analysis by Subin K Mohan
France's Top 5 Promising EdTech Companies to Watch in 2025.pdf
Cơ sở hạ tầng công nghệ thông tin trong thời đại kỹ thuật số
Nante Industrial Plug Socket Connector Sustainability Insights
Handouts for Housekeeping.pdfbababvsvvNnnh
Handouts for Housekeeping.pdfhsjsnvvbdjsnwb
757557697-CERTIKIT-ISO22301-Implementation-Guide-v6.pdf
Center Enamel Enabling Precision and Sustainability in the Netherlands' Advan...
Pink Cute Simple Group Project Presentation.pdf
Oracle Cloud Infrastructure Overview July 2020 v2_EN20200717.pptx

OEE - The Critical KPI to Drive Manufacturing Productivity

  • 1. 1 TM Overall Equipment Effectiveness TM The Critical KPI to Drive Manufacturing Productivity
  • 2. 2 TM A net reduction in cost of operations directly and positively affects the bottom line. Companies can boost revenue without sacrificing profitability by factoring in long-term debt-to-capital ratio. Since finance puts a premium on a company’s ability to maximize productivity and use existing assets, you have to continually measure, analyze, and adjust your processes. This is accomplished by a rigorous practice of productivity gains, cost cutting with increased efficiencies, and maximizing returns on fixed assets. Though complex, this productivity improvement affects labor, equipment, consumables, procedures, quality, and capital investment. As part of the plan to improve, the following goals are common for most manufacturers: • Increase capacity / decrease time to produce • Increase return on assets • Reduce operating costs • Better manage capital • Increase total shareholder returns How do you accomplish these goals? An Introduction to OEE A powerful method to improve manufacturing productivity Overall Equipment Effectiveness (OEE) has emerged as a powerful method of evaluating the productivity of production systems. This ebook will be a guide to OEE – so you can lead your Operational Excellence team.
  • 3. 3 TM Definition of OEE OEE is an effective methodology to help improve the productivity of manufacturing processes. Since the early 1990s, OEE has emerged as a leading approach for accurately measuring true plant productivity. Initially, OEE was regularly associated with Total Productive Maintenance (TPM) programs. It is now being looked at as a powerful means of evaluating the Key Performance Indicators (KPIs). By definition, OEE is the product of Availability, Performance, and Quality category percentages: Where: Availability = Downtime Losses Performance = Speed Losses Quality = Defect Losses OEE = Availability * Performance * Quality Total Productive Maintenance (TPM) is a maintenance system covering life of all equipment: planning, manufacturing, and maintenance. Improving performance via elimination of the 6 major types of waste. OEE is the formula for defining equipment effectiveness in a TPM program. 3
  • 4. 4 TM OEE is made up of three categories: Each one of these OEE components represents losses that result in a reduction of Production Time. We begin with Total Available Time and subtract time losses due to Availability (Downtime), Performance (Speed), and Quality (Reject/Rework). Very quickly, one can see the effects of these losses on production time. Productive Time becomes a fraction of Total Available Time. By using and understanding the losses, you can take the actions necessary to increase Productive Time as much as possible. Figure 1 illustrates the time losses due to various OEE categories. Understanding OEE Terminology Figure 1 – Time Losses *Planned Shutdown Time, or time when the productive capacity is not needed, is not normally Total Available Time Planned Production Time Planned Shutdown* Operating Time Availability Loss Net Operating Time Performance Losses Productive Time Quality Losses }OEE Availability The ratio of the Operating Time to the Planned Production Time Performance The rate at which equipment converts available time into product. Calculation excludes availability and quality losses. Quality Percentage of parts which meet specifications. OEE recognizes quality as only one aspect of equipment utilization. included in the OEE calculation.
  • 5. 5 TM Total Available Time: This is the time the plant is open and could be used for production (excluding holidays). Planned Production Time: This is the Total Available Time minus the Planned Shutdown Time. Planned Shutdown could include meal breaks, or scheduled maintenance; changeover is often categorized as loss of Planned Production Time. Operating Time: This is the difference between Planned Production Time and the time lost to downtime. Downtime events include equipment breakdown, unscheduled maintenance, setup time and changeover. This is included in the OEE calculations. Net Operating Time: This is the difference between the Operating Time and time lost to Speed reduction. Speed reduction events include operating equipment at below rated speed (increased cycle time), frequent short-lived stoppages not requiring maintenance, and certain operator errors. This is included in the OEE calculations. Productive Time: This is the difference between the Net Operating Time and the time lost to Quality issues. Quality losses include rejected and reworked products. This is included in the OEE calculations. Figure 1 describes how each OEE Category is calculated. 5
  • 6. 6 TM OEE Calculations Downtime Losses Availability: The ratio of Operating Time to Planned Production Time (Operating Time is Planned Production Time Less Downtime Loss). Availability of 100% means the process has been running with no stops. Availability = Operating Time / Planned Production Time Speed Losses Quality Losses Quality: The ratio of Good Parts to Total Parts. Quality of 100% means there have been no reject or rework parts. Quality = Good Parts / Parts Produced Performance: The ratio of Theoretical/Ideal Speed to Actual Speed. Performance of 100% means the process has been consistently running at its theoretical maximum speed. Performance = Parts Produced / (Ideal Speed * Operating Time)
  • 7. 7 TM Defining OEE Events Within each OEE Category, there are several events that must be identified, correctly measured, and analyzed. There are situations (or events) that may require further thought to decide to which category they belong. For example, short-lived stops and operator errors could be recorded as either Availability (Downtime) or Performance (Speed) losses. The correct categorization will be made based on the specific manufacturing process and plant. It is important to be consistent and uniform in categorizing events in order to get reliable results. As stated above, there are many events that affect OEE. By implementing an OEE practice, you can reduce these commonly occurring loss events to increase the overall plant productivity. Figure 2 provides a list of the Common Loss Events, and the attributed categories. Common Events OEE Category Comment Equipment Breakdowns Availability Loss Depending on the specifics of the production environment, certain variety of breakdowns not requiring maintenance could be categorized as Performance/Speed Losses Process Setup and Adjustments Availability Loss Includes certain operator errors and product changeovers Short Stops and Idling Performance Loss Short stops are typically those which do not require maintenance. Generally, problems with consumables could be categorized as Performance/Speed Losses Reduced Speed Performance Loss Factors such as equipment age or production anomalies that keep the operation from running at the maximum theoretical speed would be included in this category Startup Rejects Quality Loss Production loss (rejected) during initial stages (transition) of startup prior to reaching steady state (regularly producing good products) Production Rejects Quality Loss Products lost (rejected due to defect) during the normal production stages Figure 2
  • 8. 8 TM The purpose of implementing an OEE program is to improve productivity. It is important to know what you are aiming to achieve. What is considered to be world-class OEE? Are the components of OEE important by themselves? These are very significant questions. By general consensus, world-class OEE is 85% or higher. By contrast, most manufacturing plants have an OEE in the range of 30 – 60%. It is not unusual for these plants to experience daily fluctuations of about 10% - there is room for improvement. What is Considered World-Class OEE? Availability 90% Performance 95%x x Quality 99.9% Overall OEE 85%= Components of World-Class OEE
  • 9. 9 TM Achieving world-class OEE is quite challenging and requires the need to consistently follow a rigorous program. This means regular measurement, analysis, and taking action based on the findings. An important point to keep in mind is that you must look at all four numbers (OEE, Availability, Performance, and Quality) together and individually. Though it may sound contradictory since OEE is a measure of productivity, it is possible to have a reasonable OEE without having an acceptable individual component score. With each component of OEE being counted equally (A*P*Q), each needs to be diligently inspected. Don’t forgo quality (more rejects or rework) to increase output or performance. If the balance in achieving a higher OEE is off, the outcome may be unacceptable. Scrutinize each component of OEE: Quick tip • Availability • Performance • Quality • Overall OEE A PQ P AQ Q AP
  • 10. 10 TM Benchmark OEE In a recent survey conducted by LNS Research, nearly 200 companies across multiple disciplines reported their OEE numbers. From these findings, it seems world-class OEE is being met in a number of factories – especially in Life Sciences and Discrete – but just how far is this from reality? From these ranges, the numbers seem to be significantly inflated compared to the reality of most manufacturers. The OEE of these industries tend to be more shocking in practice. With the proper methodology, technical ability, and infrastructure in place, you can achieve world-class manufacturing numbers. You cannot misrepresent the numbers if you plan to act on them. Get accurate, automated, real time insight into your shop floor with TrakSYS™. Let’s look at a real life example. Highest Reported OEE Median OEE Lowest Reported OEE Average OEE Range 100 10 20 30 40 50 60 70 80 90 Batch Manufacturing 94 75 58 Discrete Manufacturing 99 85 50 Food & Beverage / CPG 95 78 55 Life Sciences 98 85 45 Process Manufacturing 94 80 72
  • 11. 11 TM It is good to know what OEE and its components are but in order to have a good understanding of the concept, it is helpful to look at a real example. Consider a beverage plant with the following production schedule for the bottling area: A Real Example Figure 4 - Production Data for Calculation of OEE and its Components Item Data Days of Operation Planned 5 Number of Shifts 15 (3 per day, 8 hrs. each) Total Planned Shutdown 2,400 minutes (160 minutes/shift) Downtime 1,250 minutes (for all shifts) Theoretical (Ideal) Rate 600 bpm (bottles per minute) Total Bottles Produced 1,656,502 Rejected Bottles 1,207
  • 12. 12 TM The Breakdown Planned Production Time Total Available Time – Total Planned Shutdown Operating Time Planned Production - Downtime Good Bottles Total Bottles - Rejected Bottles 7,200 - 2,400 = 4,800 minutes 4,800 - 1,250 = 3,550 minutes 1,656,502 - 1,207 = 1,655,295 Availability Operating Time / Planned Production Time Quality Good Bottles / Total Bottles Produced Performance Bottles Produced / (Ideal Rate * Operating Time) 3,550 / 4,800 = 0.73 (or 73%) 1,655,295 / 1,656,502 = 0.99 (or 99%) 1,656,502 / ( 600 bpm * 3,550 ) = 0.7777 (or 77%) Real-Time Plant Data Calculated Metrics OEE Availability * Performance * Quality 0.73 * 0.77 * 0.99 = 0.57 (or 57%) KPI
  • 13. 13 TM 13 Considering that OEE can also be defined as: OEE = Productive Time / Planned Production Time Then: Productive Time = OEE * Planned Production Time = 0.5748 * 4,800 minutes = 2,759.04 minutes Also, consider if downtimes and short-lived stoppages were reduced by 10% or 125 minutes, the same factory would be able to produce 58,327 more bottle during the same five-day period (assuming the same effective performance). With the wholesale price of each bottle at $0.85, during each five-day period, the bottling area can produce $49,578 more sellable product. If the bottling area is operating 260 days during the year, the extra production will be worth $2,578,056 without extra shifts or overtime.
  • 14. 14 TM Global competition dictates the need to optimize assets, labor, and processes, making Overall Equipment Effectiveness (OEE) an essential KPI. Though important for continuous improvement, many companies still struggle with collecting accurate OEE data and characterizing the root cause(s) behind variations in productivity. A manual process to collect OEE data, e.g. clipboards and whiteboards, is often inaccurate, delayed, and/or involves extra paperwork and operator dependencies. The next improvement step is to implement software capable of directly monitoring the control systems running the plant assets. Web-based reports, automated alerts via email or text message, and web journals create a highly engaged and responsive team for significant improvement. These results will tie directly to specific plant initiatives, whether expanding capacity of the existing assets, reducing changeover times, reducing overtime, reducing rework and scrap, or improving customer service levels. Conclusion To learn more, visit pages.parsec-corp.com/productivity.html or contact us [email protected]
  • 15. 15 TM About Parsec Parsec Automation Corp. (Parsec) is the developer of TrakSYS™, the leading real-time operations & performance management software. Manufacturing companies worldwide rely on Parsec for flexible and configurable tools to execute manufacturing operations across the value chain more effectively. Without production disruption, TrakSYS™ helps manufacturers to significantly improve asset utilization and efficiency, increase capacity with no new capital equipment, reduce production costs, decrease lead time, and improve profitability. With measurable ROI, TrakSYS™ fuels Lean, Six Sigma, TPM, and Operational Excellence efforts. For more information about Parsec, please visit the corporate Web site at www.parsec-corp.com. © 2015