THE LAW OF TENDERING 
FMC LLP Construction Group
March 4, 2010 




                             1
TENDERING
presented by:
Phil Scheibel




                2
LAW OF TENDER
 A.  Overview

 1.   R. v. Ron Engineering & Construction (Eastern) Ltd., [1981] 1 S.C.R. 111.

 •    Case introduced the Contract A/Contract B analysis.

 •    Contract A is formed immediately upon a bidder submitting a bid in 
      response to an invitation to tender.

 •    Contract B is formed between the owner and the winning bidder and is the 
      actual construction contract.




                                                                                  3
Law of Tender (cont.)
     2.   M.J.B. Enterprises Ltd. v. Defence Construction (1951) Ltd., [1999] 1 S.C.R. 619.

     •    Central issue was whether the inclusion of a privilege clause in the tender 
          documents allows the person calling for tenders to disregard the lowest bid in 
          favour of any other tender including a non‐complaint one. 
     •    Court clarified that Contract A can only be formed between an owner and 
          compliant bids, meaning an owner can only accept compliant bids:

           •   The rationale for the tendering process…is to replace negotiation with competition.  
               This competition entails certain risks for the [contractor].  The [contractor] must 
               expend effort and incur expense in preparing its tender in accordance with strict 
               specifications and may nonetheless not be awarded Contract B…it appears obvious to 
               me that exposing oneself to such risks makes little sense if the [owner] is allowed, in 
               effect to circumscribe this process and accept a non‐compliant bid.  Therefore I find it 
               reasonable, on the basis of the presumed intentions of the parties, to find an implied 
               term that only a compliant bid would be accepted.




                                                                                                           4
Law of Tender (cont.)
  • The tender call is the owner's offer to receive and consider tenders according 
    to the terms and conditions of the tender call.

  • The submission of a compliant tender is the act of acceptance of the owner's 
    offer.

  • The court will apply a test of "substantial" compliance so that technical 
    deficiencies which would not operate to undermine the integrity of the 
    tendering process have been held not to invalidate a tender.




                                                                                      5
Law of Tender (cont.)
   • It is not the law that the owner can only accept the lowest compliant bid —
     there is no incompatibility between the privilege clause and the prohibition 
     on accepting non‐compliant tenders.

   • An owner is entitled to take a "nuanced" view of price.  Examples of 
     economic factors an owner is entitled to take into account in rejecting the 
     lowest tender include:

        • Additional contract administration costs anticipated as a result of the tenderer's
          previous performance on other projects.
        • Tenderer's lack of actual direct experience in performance of the work.
        • Potential for cost increases or claims.
        • Application of alternative unit pricing.
        • Anticipated cost overruns due to past incidents of inadequate site supervision and 
          construction errors.




                                                                                                6
Law of Tender (cont.)
    3. Martel Building Ltd. v. R., [2000] 2 S.C.R. 860.
    • There is a duty to treat all compliant bidders fairly and 
       equally in accordance with the terms and conditions of the 
       tender call:
        •   In light of the costs and effort associated with preparing and 
            submitting a bid, we find it difficult to believe that the 
            [contractor] would have submitted a bid unless it was 
            understood by those involved that all bidders would be treated 
            fairly and equally … Without this implied term, tenderers whose 
            fate could be predetermined by some undisclosed standards, 
            would either incur significant expenses in preparing futile bids
            or ultimately avoid participating in the tender process.




                                                                               7
Law of Tender (cont.)
    • Prohibited activities include:
         •   Application of undisclosed preferences.
         •   Application of undisclosed bid evaluation criteria.
         •   Bid shopping.
         •   Giving one bidder an unfair competitive advantage over others.

    • At the same time, the Court reinforced that owners have the right 
      to reserve privileges to themselves:
               • …the tender documents must be examined closely to determine the full 
                 extent of the obligation of fair and equal treatment.  In order to respect the 
                 parties' intentions and reasonable expectations, such a duty must be defined 
                 with due consideration to the express contractual terms of the tender.




                                                                                                   8
Law of Tender (cont.)
     4. Double N Earthmovers Ltd. v Edmonton (City), [2007] 1 S.C.R. 
        116

     •   Court clarified the obligations on an owner in assessing 
         whether a bid is compliant.
     •   The duty of fairness requires an owner to evaluate tenders 
         "on the basis of what is actually in the bid, not to weigh them 
         on the basis of subsequently discovered information".
     •   Imposing a post‐tender investigative duty on the owner 
         "would encourage un warranted and unfair attacks by rival 
         bidders and invite unequal treatment of bidders by owners.  
         This would frustrate, rather than enhance, the integrity of the 
         bidding process."




                                                                            9
Law of Tender (cont.)
    • In other words, an owners obligations under Contract A to 
      unsuccessful bidders, including the obligation to treat bidders fairly, 
      do not survive the creation of Contract B.

    • The significance of the decision is two fold.

         • Owners and successful bidders can amend Contract B to account for 
           changed circumstances following the tender call without fear of lawsuits 
           from disgruntled bidders.
         • So long as the tender documents provide, the owner can negotiate with 
           the lowest bidder prior to contract award.




                                                                                       10
Law of Tender (cont.)
    B.   Summary of the Law of Tender

    •    Both owners and bidders have obligations.
    •    An owner must follow the terms and conditions of the tender 
         documents, can only accept compliant bids and must act fairly 
         and equally towards all bidders.
    •    A bidder cannot revoke its bid once tenders close (unless 
         permitted by the tender terms and conditions).
    •    An owner can draft criteria for contract award and insert privilege 
         clauses and reserve to itself the right to accept other than the
         lowest bid, or to not make any award at all — but there is a limit 
         and clauses which purport to eliminate the duty of fairness and 
         render the tender selection process arbitrary will be qualified by 
         the duty to treat all bidders fairly.




                                                                                11
Law of Tender (cont.)
    •   Two Percolating Issues

        •   Tender v. RFP
        •   Exclusion Clauses 




                                 12
THE TERCON DECISION
    presented by:
     Peter Vetsch




                      13
Facts
• RFEI issued by Province of British Columbia re: design and construction of  highway 
    – Six respondents provided EOIs, including Tercon and Brentwood – concern with 
        Brentwood’s lack of drilling/blasting experience 
    – Province then decided to design the highway itself and to bid out construction work only 
        to RFEI respondents

• RFP therefore issued, expressly limited to the six initial RFEI respondents only:  “Proposals 
  received from any other party will not be considered”.
    – Exclusion Clause in RFP:  “Except as expressly and specifically permitted in these 
        Instructions to Proponents, no Proponent shall have any claim for any compensation of 
        any kind whatsoever, as a result of participating in this RFP, and by submitting a Proposal 
        each Proponent shall be deemed to have agreed that it has no claim.”




                                                                                                  14
Facts (cont.) 
    – Brentwood entered into pre‐bidding joint venture agreement with larger construction 
      company, EAC (not an eligible Proponent)
    – Brentwood formally informed the Province of existence of joint venture prior to
      submitting its bid.  Both agreed that the joint venture was likely an ineligible bidder.  The 
      Province therefore told Brentwood to submit the RFP in its name only, which 
      Brentwood did, listing EAC as a major subcontractor.  

• Brentwood and Tercon were the two short‐listed RFP Proponents and Brentwood 
  was ultimately chosen for the highway construction project

• Tercon sued, alleging that (1) in breach of Contract A, the Province had accepted an 
  ineligible bidder (i.e. the Brentwood/EAC joint venture), and that (2) the Exclusion 
  Clause did not save the Province from this kind of fundamental breach.




                                                                                                   15
Lower Courts
•    BC Supreme Court: found in favour of Tercon and awarded $3.5M in damages for Tercon’s
    loss of the construction contract


• Held that:
               – (1) The RFP was sufficiently formal and imposed a sufficient level of obligation 
                 on bidders to create Contract A.
               – (2)  The Province had breached both the express provisions of Contact A and its 
                 implied obligations of good faith, fairness and equal treatment of all bidders by 
                 awarding the project to an ineligible bidder.  
               – (3)  This constituted a fundamental breach of Contract A – neither fair nor 
                 reasonable to uphold Exclusion in such circumstances.




                                                                                                      16
Lower Courts (cont.) 
• BC Court of Appeal:  reversed the trial decision and found in favour of the Province


• Held that:

               – (1)  The plain wording of the exclusion clause was clear and unambiguous, broad 
                 enough to cover the Province’s breach – no recovery to Tercon




                                                                                                    17
Supreme Court of Canada
• Whole Court:
   – The time has come to “lay to rest” the doctrine of fundamental breach 
   – Courts will no longer refuse to enforce an exclusion clause simply 
     because the defendant’s breach “went to the very root of the 
     contract” or “denied the plaintiff of substantially the whole of the 
     benefit of the contract”




                                                                          18
Supreme Court of Canada (cont.)
• Majority (5 judges): agreed with the BC Supreme Court; overturned Court 
  of Appeal


• Held that: 
   – (1) Brentwood’s accepted bid was made on behalf of ineligible joint 
      venture, (2) the joint venture materially improved Brentwood’s bid, 
      and (3) the Province knew this and so intentionally attempted to
      conceal the winning proponent’s true identity  – Clear breach of 
      express and implied terms of Contract A




                                                                             19
Supreme Court of Canada ( Majority 
cont.)
 – The exclusion clause barring Proponent claims resulting from “participating in this RFP”
   did not bar Tercon’s claim:

      • RFP process premised on closed list of six bidders
      • Contest involving ineligible bidder therefore fell outside of that process
      • A process involving other bidders…is not the process called for by ‘this RFP’ and 
        being part of that other process is not in any meaningful sense ‘participating in this 
        RFP’.” (para. 74)  
      • “Tercon’s claim is not barred by the exclusion clause because the clause only applies 
        to claims arising ‘as a result of participating in [the] RFP’, not to claims resulting from 
        the participation of other, ineligible parties.” (para. 63) 




                                                                                                  20
Supreme Court of Canada (Majority cont.)
• “Clear language” necessary to exclude liability for a breach of Contract A’s implied 
  duty of fairness and obligation to treat all bidders fairly and equally, especially in 
  public procurement context 

    – Still possible to exclude such liability by using the right wording in Contract A?




                                                                                            21
Supreme Court of Canada (Majority cont.)
• An early return of the doctrine of fundamental breach?  Majority’s 
  rationale for not upholding the exclusion clause: 

    – Restricted eligibility of bidders was “the foundation of this RFP” – Court 
      should interpret the exclusion clause compatibly with eligibility limitations 
      which were “at the very root of the RFP”.  (para. 70) 
    – Parties would not have intended exclusion to “effectively gut” a key aspect of 
      approved RFP process (para. 72) or waive compensation for conduct that 
      “strikes at the heart of the integrity and business efficacy of the tendering 
      process”.  (para. 78)
    – Limiting bidders to the six RFEI respondents “was the foundation of the whole 
      RFP”, and acceptance of an ineligible bid “attacks the underlying premise of 
      the process”, such that “[l]iability for such an attack is not excluded by a clause 
      limiting compensation resulting from participation in this RFP.” (para. 76)

• CONCLUSION:  Exclusion clause held not to cover the breach; Tercon’s claim for 
  damages successful



                                                                                         22
Supreme Court of Canada (Dissent)
• Dissent (4 judges): would have upheld the exclusion clause and denied claim 

• Held that:
   – Contract A not based on “some abstract externally imposed rule of law” but on the 
       presumed intent of the actual parties to the contract 




                                                                                          23
Supreme Court of Canada (Dissent cont.)
 – 3‐step inquiry when party seeks to escape a contractual exclusion clause:

      • 1.  As a matter of interpretation, does the exclusion clause even apply to the 
        circumstances of the case?
      • 2.  If yes, was the exclusion clause unconscionable at the time the contract was 
        made?  (relates to contract formation, not breach)
      • 3.  If the clause was valid when it was made, should the Court nevertheless refuse to 
        enforce it because of some overriding public policy that outweighs the very strong 
        public interest in the enforcement of contracts?
           – Burden of proof on the party seeking to avoid exclusion
           – Examples of public policy exceptions:  fraud, conduct approaching criminality




                                                                                             24
Supreme Court of Canada (Dissent cont.)
• 3‐step approach applied by dissent:

          • 1.  Does the exclusion apply?  Yes.
              – Exclusion clear and unambiguous  
              – “Participating in this RFP” = more than Province’s final selection of an ineligible 
                 bid; begins with submitting a Proposal and having it considered 
              – Tercon clearly “participated in this RFP” and fell within plain wording of the 
                 exclusion.  
              – The Province “was at fault in its performance of the RFP, but the conclusion that 
                 the process thereby ceased to be the RFP process appears to me…to be a 
                 strained and artificial interpretation [of the exclusion] in order, indirectly and 
                 obliquely, to avoid the impact of what seems…ex post facto to have been an 
                 unfair and unreasonable clause.” (para. 128)




                                                                                                   25
Supreme Court of Canada (Dissent cont.)
    • 2. Was the exclusion unconscionable when made? No. 

       – No unequal bargaining power  
       – Tercon a major contractor with experience entering into tender contracts “and 
         is well able to look after itself”. 




                                                                                          26
Supreme Court of Canada (Dissent cont.)
    • 3.  Are there public policy reasons not to enforce the exclusion? No.
       – Tercon failed to prove that Province’s actions were “so aberrant as to forfeit the 
         protection of the contractual exclusion clause on the basis of some overriding 
         public policy.” (para. 135)
       – No reason to deprive Province of “the protection of the clear exclusion clause 
         freely agreed to by Tercon.” (para. 140)
       – If Tercon did not think it was in its business interest to bid on project based on 
         RFP exclusion, it was free to decline to participate.  “So long as contractors are 
         willing to bid on such terms, I do not think it is the court’s job to rescue them 
         from the consequences of their decision to do so.” (para. 141)




                                                                                           27
RFPs vs. TENDERS
  Presented by:
 E. Jane Sidnell




                   28
Pros and Cons of Tenders and RFPs
• Pros of Tenders                           • Pros of RFPs
   – Drives to lowest cost delivery            – Scope does not need to be set
     method                                    – Flexibility to receive suggestions 
   – Irrevocable price                           from proponents
   – If selected bidder refuses to enter       – No duty of fairness on part of 
     into Contract B, owner can sue              Owner
     for damages (i.e. differential to 
     next selected or lowest bidder)
                                            • Cons of RFPs
• Cons of Tenders                              – Proponent can pull out at any 
   – Most practical where scope if               time ~ price is revocable
     defined                                   – Does not focus the selection on 
   – Owner has a duty of fairness                the lowest cost delivery method
   – Owner must comply with the                – Owner still may have duties
     rules of engagement and can face 
     significant exposure for failing to 
     do so


                                                                                       29
Considerations for Decision Making
Tender       Consideration                                                         RFP
 Typically   Is the work or are the services clearly specified?                    Does not 
                                                                                    matter
   Yes       Are the final results and deliverables clearly defined?               Does not 
                                                                                    matter
   Yes       Is more weight placed on price than other values?                        No

   Yes       Is price irrevocability important to the owner?                          No

    No       Does owner want input on design ,execution, alternative methods or       Yes
             innovations?
   Yes       Is there mandatory detailed evaluation criteria?                         Not 
                                                                                    typically
   Yes       Does owner want a specific form of contract?                             No



                                                                                                30
What makes an RFP a Tender?
• Indicia of tenders:
   – Irrevocability of submission
   – Security required with submission
   – Revisions required to be in writing, executed and received before the 
     closing
   – Detailed evaluation criteria specified and the limited criteria being the 
     only criteria used to evaluate the bids
   – Detailed pricing provisions that are fixed and non‐negotiable
   – Contract B to be substantially in the form attached to the package




                                                                                  31
Effect of an Exclusion Clause
• Justice Cromwell also determines that:
   – the existence of an exclusion clause is in itself an indicia of a tender 
     because an exclusion clause would not be necessary for an RFP
   – it is not fatal that the “classic” approach was not followed:
       • Classic: Contract A – Contract B framework in which bidder submits an 
         irrevocable bid and undertakes to enter into Contract B on those terms if 
         its bid is accepted
       • Tercon variation: Contract B to follow good faith negotiations based on the 
         form set out in the tender documents




                                                                                    32
Avoiding the Tender Conundrum
• Steps to take to keep your RFP out of the world of tender:
   – State that the process is not a tender process
   – Scope of work may allow for input by proponents – specifications need 
     not necessarily followed by proponent – alternate methods welcomed
   – Use subjective evaluation criteria without significant detail or process 
     ~ do not evaluate on price
   – Allow for proposals to be revoked
       • There will be no need for:
          – bid security
          – an exclusion clause
   – Consider whether attaching contractual terms is necessary




                                                                             33
EXCLUSION CLAUSES
   presented by:
Robert Simpson Q.C.




                      34
The Exclusion Clause
• "The Exclusion Clause reads:

   – 2.10        …Except as expressly and specifically permitted in these 
     instructions to Proponents, no Proponent shall have any claim for 
     compensation of any kind whatsoever, as a result of participating in 
     this RFP, and by submitting a Proposal each Proponent shall be 
     deemed to have agreed that it has no claim."




                                                                             35
The Basic Principles Applying to 
Exclusion Clauses
• Exclusion clauses that are drafted to address the claim being advanced will be 
  respected and applied if they are clear and comprehensive such that the wording of 
  the clause is found to apply to the circumstances established in the evidence. 

• An exclusion clause, however, will be construed strictly to determine whether it 
  applies to the circumstances of the claim.

• Clear language which addresses the precise circumstances of the claim is necessary 
  to exclude liability.

• To determine if an exclusion clause is applicable, the exclusion clauses must not be 
  read in isolation but should be considered in harmony with the rest of the contract 
  and in light of its purposes and commercial context. 




                                                                                          36
The Majority's Analysis on the 
Application of the Exclusion Clause
• The majority found that the exclusion clause did not apply to the 
  circumstances of the Tercon's claim.  It did so because:

   – In looking at the other provisions of the RFP, the Court found that the Province 
     reserved its right to unilaterally cancel the RFP and propose a new RFP to 
     additional bidders and did not reserve to itself the right to accept a bid from 
     an ineligible bidder or to unilaterally change the rules of eligibility; 

   – The Court found that the integrity and business efficacy of the tendering 
     process supported an interpretation that would allow the exclusion clause to 
     operate compatibly with the eligibility limitations that were at the very root of 
     the RFP;




                                                                                      37
The Majority's Analysis on the 
Application of the Exclusion Clause (cont.)
  – The implied duty of fairness which is a basic requirement of the tendering 
    process, particularly in the case of public procurement was not explicitly 
    excluded by the wording of the clause;

  – The Court found that even though the application of the exclusion clause was 
    restricted, it still had application and could be given effect in the proper 
    circumstances.  The Court pointed out that the exclusion clause would apply if 
    the remedy claimed was not for compensation, although the Court noted that 
    practically speaking it could not envision a practical claim arising from a breach 
    of contract "A" other than a claim for compensation; and 

  – The exclusion clause would have application in respect of a claim that arose as 
    between the invited Proponents to the RFP.




                                                                                      38
The Majority's Conclusion
• The Court found that it was central to the RFP process issued by the Province that it 
  was a contest among those eligible to participate which did not include Proponents 
  who did not initially submit a response to the RFEI and specifically indicated that 
  Proposals received from any other party would not be considered.

• The Court found that the Proposal submitted by Brentwood was a joint venture 
  with the result that it was submitted by another party that had not submitted an 
  RFEI. 

• As the Province was now considering an ineligible party's bid, the bidding process 
  was no longer the "RFE Process" referred to in the exclusion clause but a different 
  process.

• The result found was that the exclusion clause did not apply to this different RFE 
  Process.


                                                                                         39
The Minorities' View
• There is nothing inherently unreasonable about exclusion clauses and they should 
  be applied unless there is some compelling reason not to give effect to the words 
  selected by the parties. 

• It is a matter of interpretation whether the exclusion clause applies to the 
  circumstances established in the evidence which will depend on the Court's 
  assessment of the intention of the parties expressed in the contract.

• Participation in the RFP began with submitting a Proposal.  As Tercon had 
  submitted a Proposal, the exclusion clause applied with the result that Tercon "shall 
  be deemed to have agreed that it has no claim". 

• The minority found that the exclusion clause applied to exclude Tercon's claim. 




                                                                                       40
What do we take from this?
• The application of an exclusion clause in any given circumstance depends 
  upon the view of the beholder.  

• That view is tainted by whether or not the beholder thinks in the 
  circumstances of the case it is fair or not to deny the claimant
  compensation.

• It is extremely difficult, if not impossible, to draft an exclusion clause that is 
  guaranteed to be effective in responding to all possible claims that could 
  arise as it is impossible to predict the manner and nature of all possible 
  claims that may arise in advance. 




                                                                                    41
How could the Province's Exclusion 
Clause be worded to avoid the Tercon
Claim?
• 2.10…Except as expressly and specifically permitted in these 
  instructions to Proponents, no Proponent shall have the right 
  to bring any claim for any remedy of any kind whatsoever as a 
  result of anything of any nature whatsoever done or not done 
  by the Province in connection with the Province's request for a 
  submission of a bid and the final award of a contract to build 
  this highway.




                                                                 42
Is the revised Exclusion Clause
bullet proof?
• As Bennie J. states in the Tercon decision, it will depend on whether a 
  Court is prepared to take a "strained and artificial interpretation in order, 
  indirectly and obliquely, to avoid the impact of what seems to it ex post 
  facto to have been an unfair and unreasonable clause";

• The facts and circumstances giving rise to the claim; and 

• There is an absence of fraud or equally evil wrongdoing on the part of the 
  party relying on the exclusion clause.




                                                                                   43
Thank You!
Contact Us:
Phil Scheibel – phil.scheibel@fmc‐law.com | +1 403 268 6810
E. Jane Sidnell – jane.sidnell@fmc‐law.com | +1 403 268 3119
Robert Simpson, Q.C. – robert.simpson@fmc‐law.com | +1 403 268 7021
The preceding presentation contains examples of the kinds of 
issues companies dealing with tendering issues could face.
If you are faced with one of these issues, please retain professional 
assistance as each situation is unique.

More Related Content

PPTX
Tender Process | A Complete Procurement Guide
PPTX
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
PPTX
Law of Contract in Malaysia (Updated 2019)
PDF
Pagine da Lo scouting del portiere: ricerca, selezione e promozione del talen...
PPTX
General Principles of Offer and Invitation to Treat
PPTX
Tendering & Procurement Overview
PDF
Breakfast for the Mind: Issues with Procurement & Tendering
PPTX
Tendering and Procurement Best Practices
Tender Process | A Complete Procurement Guide
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Law of Contract in Malaysia (Updated 2019)
Pagine da Lo scouting del portiere: ricerca, selezione e promozione del talen...
General Principles of Offer and Invitation to Treat
Tendering & Procurement Overview
Breakfast for the Mind: Issues with Procurement & Tendering
Tendering and Procurement Best Practices

Viewers also liked (10)

PDF
Pwd 203 a rev2007
PDF
Fraud Risk Assessment- detection and prevention- Part- 2,
PPTX
Tendering and Procurement - Basic Principles
PPTX
The Basics of Tendering & Bidding
PDF
Tendering documentation
PPTX
Tender processing
PPT
Tender evaluation procedure
PPTX
Tender procedure slide
PDF
Estimating and-costing book
Pwd 203 a rev2007
Fraud Risk Assessment- detection and prevention- Part- 2,
Tendering and Procurement - Basic Principles
The Basics of Tendering & Bidding
Tendering documentation
Tender processing
Tender evaluation procedure
Tender procedure slide
Estimating and-costing book
Ad

Similar to The Law of Tendering (17)

PPTX
Tendering and Procurement Basics
PDF
CVC_ZTC-copy - Copy
PPTX
TENDERING PROCESS, TYPES OF TENDERS, TENDER DOCUMENT
PDF
Public Construction Procurement - Key Cases Defining the Public Procurement L...
PPT
TENDER-Revised vigilance perspective. this helps administration
PPTX
Procurement and Subcontractors
PDF
3 tender stage
DOCX
Document samples
PDF
Tender and tender document
PPTX
Ppt on unit 8 Electrical Design Estimate
DOCX
Analysis of Ron Engineering V the Crown by Okafo EKE
PPTX
Contracts.pptx
PPTX
Tender & its process.pptx
PPT
Contract Management - Basics.ppt
PPTX
Unit-2_Tender
PPTX
Legal_Case_Study_Tender_Rvvejection.pptx
PPTX
fdfLegal_Case_Study_Tender_Rejection.pptx
Tendering and Procurement Basics
CVC_ZTC-copy - Copy
TENDERING PROCESS, TYPES OF TENDERS, TENDER DOCUMENT
Public Construction Procurement - Key Cases Defining the Public Procurement L...
TENDER-Revised vigilance perspective. this helps administration
Procurement and Subcontractors
3 tender stage
Document samples
Tender and tender document
Ppt on unit 8 Electrical Design Estimate
Analysis of Ron Engineering V the Crown by Okafo EKE
Contracts.pptx
Tender & its process.pptx
Contract Management - Basics.ppt
Unit-2_Tender
Legal_Case_Study_Tender_Rvvejection.pptx
fdfLegal_Case_Study_Tender_Rejection.pptx
Ad

More from Now Dentons (20)

PDF
Meet dentons
PDF
FMC is Now Dentons
PDF
Foreign Workers, International Tax and Oil & Gas Market Update
PDF
Protecting Your Start-Up Company's IP
PDF
Privacy and Security in Mobile E-Commerce
PDF
Drafting for the Matrimonial Property Act
PDF
Trends in Energy Regulatory Law
PDF
Public M&A Transactions - Deal Points
PDF
Giving Away the Farm
PDF
Risk Apportionment in the Purchase and Sale Transaction
PDF
Letters of Intent - Tips and Traps for Commercial Lawyers
PDF
Protect you Rights and Avoid Liability! Current Developments and Major Implic...
PDF
Preliminary Economic Assessments
PDF
An Introduction to Legal Aspects of Customer Acquisitions for Startups
PDF
An Introduction to Letters of Credit for Banking Lawyers
PDF
Preparing the Legal Framework for Mobile and Other Emerging Payments
PDF
Update on Hydraulic Fracturing: Preparing for Gasland 2
PDF
Canada, China and Copyright Law
PDF
Intellectual Property and Business Law
PDF
The Copyright Modernization Act
Meet dentons
FMC is Now Dentons
Foreign Workers, International Tax and Oil & Gas Market Update
Protecting Your Start-Up Company's IP
Privacy and Security in Mobile E-Commerce
Drafting for the Matrimonial Property Act
Trends in Energy Regulatory Law
Public M&A Transactions - Deal Points
Giving Away the Farm
Risk Apportionment in the Purchase and Sale Transaction
Letters of Intent - Tips and Traps for Commercial Lawyers
Protect you Rights and Avoid Liability! Current Developments and Major Implic...
Preliminary Economic Assessments
An Introduction to Legal Aspects of Customer Acquisitions for Startups
An Introduction to Letters of Credit for Banking Lawyers
Preparing the Legal Framework for Mobile and Other Emerging Payments
Update on Hydraulic Fracturing: Preparing for Gasland 2
Canada, China and Copyright Law
Intellectual Property and Business Law
The Copyright Modernization Act

Recently uploaded (20)

PPTX
1. Ancient Civilization presentations .pptx
PPTX
Hospitality & tourism management.pptxHospitality & tourism management.pptx
DOCX
“Strategic management process of a selected organization”.Nestle-docx.docx
PDF
COVID-19 Primer for business case prep.pdf
DOCX
Handbook of entrepreneurship- Chapter 10 - Feasibility analysis by Subin K Mohan
PDF
Не GPT єдиним: можливості AI в бізнес-аналізі | Вебінар з Тетяною Перловською
 
PPTX
TS - CIM-as of august 2023 .pptx
PPTX
international business Chapter 013 global sourcing
DOCX
Tax administration and supervision for accounting
PPTX
Breaking Barriers in Tech : A Female Founder’s Story of Resilience and SaaS I...
PPTX
Oracle Cloud Infrastructure Overview July 2020 v2_EN20200717.pptx
PDF
Impact of Social Media Marketing on Buying Behaviors of Superstore Customers ...
PDF
El futuro en e sector empresarial 2024 e
PDF
The Impact of Historical Events on Legal Communication Styles (www.kiu.ac.ug)
PDF
Mukul Madhav Foundation (MMF) Newsletter – June 2025
PPTX
Enterprises are Classified into Two Categories
PPTX
UNIT 3 INTERNATIONAL BUSINESS [Autosaved].pptx
PDF
109422672-Doc-8973-05-Security-Manual-Seventh-Edition.pdf
PDF
The Relationship between Leadership Behaviourand Firm Performance in the Read...
PDF
audit case scenario .pdf by icai ca inter
1. Ancient Civilization presentations .pptx
Hospitality & tourism management.pptxHospitality & tourism management.pptx
“Strategic management process of a selected organization”.Nestle-docx.docx
COVID-19 Primer for business case prep.pdf
Handbook of entrepreneurship- Chapter 10 - Feasibility analysis by Subin K Mohan
Не GPT єдиним: можливості AI в бізнес-аналізі | Вебінар з Тетяною Перловською
 
TS - CIM-as of august 2023 .pptx
international business Chapter 013 global sourcing
Tax administration and supervision for accounting
Breaking Barriers in Tech : A Female Founder’s Story of Resilience and SaaS I...
Oracle Cloud Infrastructure Overview July 2020 v2_EN20200717.pptx
Impact of Social Media Marketing on Buying Behaviors of Superstore Customers ...
El futuro en e sector empresarial 2024 e
The Impact of Historical Events on Legal Communication Styles (www.kiu.ac.ug)
Mukul Madhav Foundation (MMF) Newsletter – June 2025
Enterprises are Classified into Two Categories
UNIT 3 INTERNATIONAL BUSINESS [Autosaved].pptx
109422672-Doc-8973-05-Security-Manual-Seventh-Edition.pdf
The Relationship between Leadership Behaviourand Firm Performance in the Read...
audit case scenario .pdf by icai ca inter

The Law of Tendering

  • 3. LAW OF TENDER A.  Overview 1. R. v. Ron Engineering & Construction (Eastern) Ltd., [1981] 1 S.C.R. 111. • Case introduced the Contract A/Contract B analysis. • Contract A is formed immediately upon a bidder submitting a bid in  response to an invitation to tender. • Contract B is formed between the owner and the winning bidder and is the  actual construction contract. 3
  • 4. Law of Tender (cont.) 2. M.J.B. Enterprises Ltd. v. Defence Construction (1951) Ltd., [1999] 1 S.C.R. 619. • Central issue was whether the inclusion of a privilege clause in the tender  documents allows the person calling for tenders to disregard the lowest bid in  favour of any other tender including a non‐complaint one.  • Court clarified that Contract A can only be formed between an owner and  compliant bids, meaning an owner can only accept compliant bids: • The rationale for the tendering process…is to replace negotiation with competition.   This competition entails certain risks for the [contractor].  The [contractor] must  expend effort and incur expense in preparing its tender in accordance with strict  specifications and may nonetheless not be awarded Contract B…it appears obvious to  me that exposing oneself to such risks makes little sense if the [owner] is allowed, in  effect to circumscribe this process and accept a non‐compliant bid.  Therefore I find it  reasonable, on the basis of the presumed intentions of the parties, to find an implied  term that only a compliant bid would be accepted. 4
  • 5. Law of Tender (cont.) • The tender call is the owner's offer to receive and consider tenders according  to the terms and conditions of the tender call. • The submission of a compliant tender is the act of acceptance of the owner's  offer. • The court will apply a test of "substantial" compliance so that technical  deficiencies which would not operate to undermine the integrity of the  tendering process have been held not to invalidate a tender. 5
  • 6. Law of Tender (cont.) • It is not the law that the owner can only accept the lowest compliant bid — there is no incompatibility between the privilege clause and the prohibition  on accepting non‐compliant tenders. • An owner is entitled to take a "nuanced" view of price.  Examples of  economic factors an owner is entitled to take into account in rejecting the  lowest tender include: • Additional contract administration costs anticipated as a result of the tenderer's previous performance on other projects. • Tenderer's lack of actual direct experience in performance of the work. • Potential for cost increases or claims. • Application of alternative unit pricing. • Anticipated cost overruns due to past incidents of inadequate site supervision and  construction errors. 6
  • 7. Law of Tender (cont.) 3. Martel Building Ltd. v. R., [2000] 2 S.C.R. 860. • There is a duty to treat all compliant bidders fairly and  equally in accordance with the terms and conditions of the  tender call: • In light of the costs and effort associated with preparing and  submitting a bid, we find it difficult to believe that the  [contractor] would have submitted a bid unless it was  understood by those involved that all bidders would be treated  fairly and equally … Without this implied term, tenderers whose  fate could be predetermined by some undisclosed standards,  would either incur significant expenses in preparing futile bids or ultimately avoid participating in the tender process. 7
  • 8. Law of Tender (cont.) • Prohibited activities include: • Application of undisclosed preferences. • Application of undisclosed bid evaluation criteria. • Bid shopping. • Giving one bidder an unfair competitive advantage over others. • At the same time, the Court reinforced that owners have the right  to reserve privileges to themselves: • …the tender documents must be examined closely to determine the full  extent of the obligation of fair and equal treatment.  In order to respect the  parties' intentions and reasonable expectations, such a duty must be defined  with due consideration to the express contractual terms of the tender. 8
  • 9. Law of Tender (cont.) 4. Double N Earthmovers Ltd. v Edmonton (City), [2007] 1 S.C.R.  116 • Court clarified the obligations on an owner in assessing  whether a bid is compliant. • The duty of fairness requires an owner to evaluate tenders  "on the basis of what is actually in the bid, not to weigh them  on the basis of subsequently discovered information". • Imposing a post‐tender investigative duty on the owner  "would encourage un warranted and unfair attacks by rival  bidders and invite unequal treatment of bidders by owners.   This would frustrate, rather than enhance, the integrity of the  bidding process." 9
  • 10. Law of Tender (cont.) • In other words, an owners obligations under Contract A to  unsuccessful bidders, including the obligation to treat bidders fairly,  do not survive the creation of Contract B. • The significance of the decision is two fold. • Owners and successful bidders can amend Contract B to account for  changed circumstances following the tender call without fear of lawsuits  from disgruntled bidders. • So long as the tender documents provide, the owner can negotiate with  the lowest bidder prior to contract award. 10
  • 11. Law of Tender (cont.) B. Summary of the Law of Tender • Both owners and bidders have obligations. • An owner must follow the terms and conditions of the tender  documents, can only accept compliant bids and must act fairly  and equally towards all bidders. • A bidder cannot revoke its bid once tenders close (unless  permitted by the tender terms and conditions). • An owner can draft criteria for contract award and insert privilege  clauses and reserve to itself the right to accept other than the lowest bid, or to not make any award at all — but there is a limit  and clauses which purport to eliminate the duty of fairness and  render the tender selection process arbitrary will be qualified by  the duty to treat all bidders fairly. 11
  • 12. Law of Tender (cont.) • Two Percolating Issues • Tender v. RFP • Exclusion Clauses  12
  • 13. THE TERCON DECISION presented by: Peter Vetsch 13
  • 14. Facts • RFEI issued by Province of British Columbia re: design and construction of  highway  – Six respondents provided EOIs, including Tercon and Brentwood – concern with  Brentwood’s lack of drilling/blasting experience  – Province then decided to design the highway itself and to bid out construction work only  to RFEI respondents • RFP therefore issued, expressly limited to the six initial RFEI respondents only:  “Proposals  received from any other party will not be considered”. – Exclusion Clause in RFP:  “Except as expressly and specifically permitted in these  Instructions to Proponents, no Proponent shall have any claim for any compensation of  any kind whatsoever, as a result of participating in this RFP, and by submitting a Proposal  each Proponent shall be deemed to have agreed that it has no claim.” 14
  • 15. Facts (cont.)  – Brentwood entered into pre‐bidding joint venture agreement with larger construction  company, EAC (not an eligible Proponent) – Brentwood formally informed the Province of existence of joint venture prior to submitting its bid.  Both agreed that the joint venture was likely an ineligible bidder.  The  Province therefore told Brentwood to submit the RFP in its name only, which  Brentwood did, listing EAC as a major subcontractor.   • Brentwood and Tercon were the two short‐listed RFP Proponents and Brentwood  was ultimately chosen for the highway construction project • Tercon sued, alleging that (1) in breach of Contract A, the Province had accepted an  ineligible bidder (i.e. the Brentwood/EAC joint venture), and that (2) the Exclusion  Clause did not save the Province from this kind of fundamental breach. 15
  • 16. Lower Courts • BC Supreme Court: found in favour of Tercon and awarded $3.5M in damages for Tercon’s loss of the construction contract • Held that: – (1) The RFP was sufficiently formal and imposed a sufficient level of obligation  on bidders to create Contract A. – (2)  The Province had breached both the express provisions of Contact A and its  implied obligations of good faith, fairness and equal treatment of all bidders by  awarding the project to an ineligible bidder.   – (3)  This constituted a fundamental breach of Contract A – neither fair nor  reasonable to uphold Exclusion in such circumstances. 16
  • 17. Lower Courts (cont.)  • BC Court of Appeal:  reversed the trial decision and found in favour of the Province • Held that: – (1)  The plain wording of the exclusion clause was clear and unambiguous, broad  enough to cover the Province’s breach – no recovery to Tercon 17
  • 18. Supreme Court of Canada • Whole Court: – The time has come to “lay to rest” the doctrine of fundamental breach  – Courts will no longer refuse to enforce an exclusion clause simply  because the defendant’s breach “went to the very root of the  contract” or “denied the plaintiff of substantially the whole of the  benefit of the contract” 18
  • 19. Supreme Court of Canada (cont.) • Majority (5 judges): agreed with the BC Supreme Court; overturned Court  of Appeal • Held that:  – (1) Brentwood’s accepted bid was made on behalf of ineligible joint  venture, (2) the joint venture materially improved Brentwood’s bid,  and (3) the Province knew this and so intentionally attempted to conceal the winning proponent’s true identity  – Clear breach of  express and implied terms of Contract A 19
  • 20. Supreme Court of Canada ( Majority  cont.) – The exclusion clause barring Proponent claims resulting from “participating in this RFP” did not bar Tercon’s claim: • RFP process premised on closed list of six bidders • Contest involving ineligible bidder therefore fell outside of that process • A process involving other bidders…is not the process called for by ‘this RFP’ and  being part of that other process is not in any meaningful sense ‘participating in this  RFP’.” (para. 74)   • “Tercon’s claim is not barred by the exclusion clause because the clause only applies  to claims arising ‘as a result of participating in [the] RFP’, not to claims resulting from  the participation of other, ineligible parties.” (para. 63)  20
  • 21. Supreme Court of Canada (Majority cont.) • “Clear language” necessary to exclude liability for a breach of Contract A’s implied  duty of fairness and obligation to treat all bidders fairly and equally, especially in  public procurement context  – Still possible to exclude such liability by using the right wording in Contract A? 21
  • 22. Supreme Court of Canada (Majority cont.) • An early return of the doctrine of fundamental breach?  Majority’s  rationale for not upholding the exclusion clause:  – Restricted eligibility of bidders was “the foundation of this RFP” – Court  should interpret the exclusion clause compatibly with eligibility limitations  which were “at the very root of the RFP”.  (para. 70)  – Parties would not have intended exclusion to “effectively gut” a key aspect of  approved RFP process (para. 72) or waive compensation for conduct that  “strikes at the heart of the integrity and business efficacy of the tendering  process”.  (para. 78) – Limiting bidders to the six RFEI respondents “was the foundation of the whole  RFP”, and acceptance of an ineligible bid “attacks the underlying premise of  the process”, such that “[l]iability for such an attack is not excluded by a clause  limiting compensation resulting from participation in this RFP.” (para. 76) • CONCLUSION:  Exclusion clause held not to cover the breach; Tercon’s claim for  damages successful 22
  • 23. Supreme Court of Canada (Dissent) • Dissent (4 judges): would have upheld the exclusion clause and denied claim  • Held that: – Contract A not based on “some abstract externally imposed rule of law” but on the  presumed intent of the actual parties to the contract  23
  • 24. Supreme Court of Canada (Dissent cont.) – 3‐step inquiry when party seeks to escape a contractual exclusion clause: • 1.  As a matter of interpretation, does the exclusion clause even apply to the  circumstances of the case? • 2.  If yes, was the exclusion clause unconscionable at the time the contract was  made?  (relates to contract formation, not breach) • 3.  If the clause was valid when it was made, should the Court nevertheless refuse to  enforce it because of some overriding public policy that outweighs the very strong  public interest in the enforcement of contracts? – Burden of proof on the party seeking to avoid exclusion – Examples of public policy exceptions:  fraud, conduct approaching criminality 24
  • 25. Supreme Court of Canada (Dissent cont.) • 3‐step approach applied by dissent: • 1.  Does the exclusion apply?  Yes. – Exclusion clear and unambiguous   – “Participating in this RFP” = more than Province’s final selection of an ineligible  bid; begins with submitting a Proposal and having it considered  – Tercon clearly “participated in this RFP” and fell within plain wording of the  exclusion.   – The Province “was at fault in its performance of the RFP, but the conclusion that  the process thereby ceased to be the RFP process appears to me…to be a  strained and artificial interpretation [of the exclusion] in order, indirectly and  obliquely, to avoid the impact of what seems…ex post facto to have been an  unfair and unreasonable clause.” (para. 128) 25
  • 26. Supreme Court of Canada (Dissent cont.) • 2. Was the exclusion unconscionable when made? No.  – No unequal bargaining power   – Tercon a major contractor with experience entering into tender contracts “and  is well able to look after itself”.  26
  • 27. Supreme Court of Canada (Dissent cont.) • 3.  Are there public policy reasons not to enforce the exclusion? No. – Tercon failed to prove that Province’s actions were “so aberrant as to forfeit the  protection of the contractual exclusion clause on the basis of some overriding  public policy.” (para. 135) – No reason to deprive Province of “the protection of the clear exclusion clause  freely agreed to by Tercon.” (para. 140) – If Tercon did not think it was in its business interest to bid on project based on  RFP exclusion, it was free to decline to participate.  “So long as contractors are  willing to bid on such terms, I do not think it is the court’s job to rescue them  from the consequences of their decision to do so.” (para. 141) 27
  • 28. RFPs vs. TENDERS Presented by: E. Jane Sidnell 28
  • 29. Pros and Cons of Tenders and RFPs • Pros of Tenders • Pros of RFPs – Drives to lowest cost delivery  – Scope does not need to be set method – Flexibility to receive suggestions  – Irrevocable price from proponents – If selected bidder refuses to enter  – No duty of fairness on part of  into Contract B, owner can sue  Owner for damages (i.e. differential to  next selected or lowest bidder) • Cons of RFPs • Cons of Tenders – Proponent can pull out at any  – Most practical where scope if  time ~ price is revocable defined – Does not focus the selection on  – Owner has a duty of fairness the lowest cost delivery method – Owner must comply with the  – Owner still may have duties rules of engagement and can face  significant exposure for failing to  do so 29
  • 30. Considerations for Decision Making Tender Consideration RFP Typically Is the work or are the services clearly specified? Does not  matter Yes Are the final results and deliverables clearly defined? Does not  matter Yes Is more weight placed on price than other values? No Yes Is price irrevocability important to the owner? No No Does owner want input on design ,execution, alternative methods or  Yes innovations? Yes Is there mandatory detailed evaluation criteria? Not  typically Yes Does owner want a specific form of contract? No 30
  • 31. What makes an RFP a Tender? • Indicia of tenders: – Irrevocability of submission – Security required with submission – Revisions required to be in writing, executed and received before the  closing – Detailed evaluation criteria specified and the limited criteria being the  only criteria used to evaluate the bids – Detailed pricing provisions that are fixed and non‐negotiable – Contract B to be substantially in the form attached to the package 31
  • 32. Effect of an Exclusion Clause • Justice Cromwell also determines that: – the existence of an exclusion clause is in itself an indicia of a tender  because an exclusion clause would not be necessary for an RFP – it is not fatal that the “classic” approach was not followed: • Classic: Contract A – Contract B framework in which bidder submits an  irrevocable bid and undertakes to enter into Contract B on those terms if  its bid is accepted • Tercon variation: Contract B to follow good faith negotiations based on the  form set out in the tender documents 32
  • 33. Avoiding the Tender Conundrum • Steps to take to keep your RFP out of the world of tender: – State that the process is not a tender process – Scope of work may allow for input by proponents – specifications need  not necessarily followed by proponent – alternate methods welcomed – Use subjective evaluation criteria without significant detail or process  ~ do not evaluate on price – Allow for proposals to be revoked • There will be no need for: – bid security – an exclusion clause – Consider whether attaching contractual terms is necessary 33
  • 34. EXCLUSION CLAUSES presented by: Robert Simpson Q.C. 34
  • 35. The Exclusion Clause • "The Exclusion Clause reads: – 2.10 …Except as expressly and specifically permitted in these  instructions to Proponents, no Proponent shall have any claim for  compensation of any kind whatsoever, as a result of participating in  this RFP, and by submitting a Proposal each Proponent shall be  deemed to have agreed that it has no claim." 35
  • 36. The Basic Principles Applying to  Exclusion Clauses • Exclusion clauses that are drafted to address the claim being advanced will be  respected and applied if they are clear and comprehensive such that the wording of  the clause is found to apply to the circumstances established in the evidence.  • An exclusion clause, however, will be construed strictly to determine whether it  applies to the circumstances of the claim. • Clear language which addresses the precise circumstances of the claim is necessary  to exclude liability. • To determine if an exclusion clause is applicable, the exclusion clauses must not be  read in isolation but should be considered in harmony with the rest of the contract  and in light of its purposes and commercial context.  36
  • 37. The Majority's Analysis on the  Application of the Exclusion Clause • The majority found that the exclusion clause did not apply to the  circumstances of the Tercon's claim.  It did so because: – In looking at the other provisions of the RFP, the Court found that the Province  reserved its right to unilaterally cancel the RFP and propose a new RFP to  additional bidders and did not reserve to itself the right to accept a bid from  an ineligible bidder or to unilaterally change the rules of eligibility;  – The Court found that the integrity and business efficacy of the tendering  process supported an interpretation that would allow the exclusion clause to  operate compatibly with the eligibility limitations that were at the very root of  the RFP; 37
  • 38. The Majority's Analysis on the  Application of the Exclusion Clause (cont.) – The implied duty of fairness which is a basic requirement of the tendering  process, particularly in the case of public procurement was not explicitly  excluded by the wording of the clause; – The Court found that even though the application of the exclusion clause was  restricted, it still had application and could be given effect in the proper  circumstances.  The Court pointed out that the exclusion clause would apply if  the remedy claimed was not for compensation, although the Court noted that  practically speaking it could not envision a practical claim arising from a breach  of contract "A" other than a claim for compensation; and  – The exclusion clause would have application in respect of a claim that arose as  between the invited Proponents to the RFP. 38
  • 39. The Majority's Conclusion • The Court found that it was central to the RFP process issued by the Province that it  was a contest among those eligible to participate which did not include Proponents  who did not initially submit a response to the RFEI and specifically indicated that  Proposals received from any other party would not be considered. • The Court found that the Proposal submitted by Brentwood was a joint venture  with the result that it was submitted by another party that had not submitted an  RFEI.  • As the Province was now considering an ineligible party's bid, the bidding process  was no longer the "RFE Process" referred to in the exclusion clause but a different  process. • The result found was that the exclusion clause did not apply to this different RFE  Process. 39
  • 40. The Minorities' View • There is nothing inherently unreasonable about exclusion clauses and they should  be applied unless there is some compelling reason not to give effect to the words  selected by the parties.  • It is a matter of interpretation whether the exclusion clause applies to the  circumstances established in the evidence which will depend on the Court's  assessment of the intention of the parties expressed in the contract. • Participation in the RFP began with submitting a Proposal.  As Tercon had  submitted a Proposal, the exclusion clause applied with the result that Tercon "shall  be deemed to have agreed that it has no claim".  • The minority found that the exclusion clause applied to exclude Tercon's claim.  40
  • 41. What do we take from this? • The application of an exclusion clause in any given circumstance depends  upon the view of the beholder.   • That view is tainted by whether or not the beholder thinks in the  circumstances of the case it is fair or not to deny the claimant compensation. • It is extremely difficult, if not impossible, to draft an exclusion clause that is  guaranteed to be effective in responding to all possible claims that could  arise as it is impossible to predict the manner and nature of all possible  claims that may arise in advance.  41
  • 42. How could the Province's Exclusion  Clause be worded to avoid the Tercon Claim? • 2.10…Except as expressly and specifically permitted in these  instructions to Proponents, no Proponent shall have the right  to bring any claim for any remedy of any kind whatsoever as a  result of anything of any nature whatsoever done or not done  by the Province in connection with the Province's request for a  submission of a bid and the final award of a contract to build  this highway. 42
  • 43. Is the revised Exclusion Clause bullet proof? • As Bennie J. states in the Tercon decision, it will depend on whether a  Court is prepared to take a "strained and artificial interpretation in order,  indirectly and obliquely, to avoid the impact of what seems to it ex post  facto to have been an unfair and unreasonable clause"; • The facts and circumstances giving rise to the claim; and  • There is an absence of fraud or equally evil wrongdoing on the part of the  party relying on the exclusion clause. 43
  • 44. Thank You! Contact Us: Phil Scheibel – phil.scheibel@fmc‐law.com | +1 403 268 6810 E. Jane Sidnell – jane.sidnell@fmc‐law.com | +1 403 268 3119 Robert Simpson, Q.C. – robert.simpson@fmc‐law.com | +1 403 268 7021