Project Status Report
Project Name: Consumer distribution changes
Department: Fulfillment
Focus Area: WA Warehouse
Prepared By: Tom Evans
Document Owner(s) Organization Role
Dave Armstrong Fulfillment team
Fiona Dickson Sales team
Project Status Report Version Control
Version Date Author Change Description
1.0 08/10/2008 Tom Evans Document created
Confidential
wawarehouseprojectstatusreport-150203194546-conversion-gate01.doc
Last printed on 10/8/2008 22:08:00 a10/p10
Project Status Report
TABLE OF CONTENTS
PROJECT STATUS REPORT PURPOSE.....................................................................................3
PROJECT STATUS REPORT .......................................................................................................3
1.1 Project Status Report Details.............................................................................................3
1.2 Project Status Report Template.........................................................................................3
PROJECT STATUS REPORT APPROVALS.................................................................................7
Confidential Page 2 2/4/2015
Project Status Report
PROJECT STATUS REPORT PURPOSE
The Project Status Report document is a means of formal regular reporting on the status of
a project to key project stakeholders, including senior management & the fulfillment / sales
teams
PROJECT STATUS REPORT
1.1 Project Status Report Details
The project status report details will include the following data & comments & be broken up
into the following categories.
• Overall status & comments
• Progress on 3PL transition
• Carrier/provider performance to date
• Warehouse sub-lease status
• Sales office relocation
• Staff morale
• IT
• Budget controls
1.2 Project Status Report Template
Project Name: Consumer distribution changes
Prepared By:
Tom Evans
Date:
08/10/2008
Reporting Period:
08/10/2008 to 15/10/2008
Project Overall Status:
Project is overall on time. There have been some initial hiccups that have resulted in some delivery
issues to store & other changes to the overall plan. None of these will result in the failure of the
overall task - the strategic exit of the WA consumer warehouse.
Confidential Page 3 2/4/2015
Project Status Report
Project Summary:
Warehouse stock transition into 3PL
• This was due this weekend but has been delayed by the provider due to unexpected stock
take from another client. This will not delay the overall project.
Freight direct to WA customers.
1. Some difficulty in this area was complicated by numerous factors. Some of which are Nylex
driven example, the failure to label deliveries correctly. Some by the carrier’s performance
due to breakdowns in the system. All aspects of this are being addressed.
2. Delivery reporting templates are being established to deliver detailed delivery reports
inclusive of delivery dates to customer – see embedded sample. This has both details from
Nylex & SCT systems
Delivery & performance reporting
Attached is a document consisting of 4 tabs relating to differing delivery status
1. “WA all Invoices” this relates to all deliveries invoice for WA in last month
2. Deliveries to WA that are in pick slip at Somerton
3. SCT delivery data including pickup times & delivery times. This is valid data & report is still a
work in progress.
4. Nylex delivery data relating to the deliveries in the SCT report.
WA Nylex SCT
bunnings delivery data.xls
**Please note SCT reporting is immature & will be available next week data in current report is live**
Warehouse sub lease status
• Colliers has worked closely with Nylex on the sob-lease option for the Nylex warehouse in
Perth. Numerous meeting have been held with Onesteel & Nylex have prepared letters of
offer to Onesteel with a start date of November 1st
. A favorable result is forecasted
Sales Office relocation
• Geoff Radford is handling the sales office relocation. Assessment of works has been carried
out & this relocation will not impact the project.
Staff morale
• Staff are coping well with the changes in the warehouse environment – no real issues to report
Geoff Radford should speak to behalf of the office staff.
Confidential Page 4 2/4/2015
Project Status Report
IT config
• Some teething problems, though Martin C has all aspects well under control for both 3pl option
& sales office config
Budget Controls
• Very little expenditure has occurred during these early stages. Costs included in attachment
Milestone Deliverables performance reporting current period
Milestone Deliverables Due Date % Completed Deliverable Status
Milestone 1 : Data analysis & planning
• A class items to 3pl
analysis
12/10/08 100% Complete
• Stock return to Melb 01/11/08 20% Pending
• Warehouse sub lease 01/11/2008 80% Pending
• Activation of 3pl 12/10/200 0% Pending /late (2 days)
• Sale office relocation 01/11/2008 50% pending
Milestone 2 Delivery testing ex Melbourne
• Bunning’s only delivery
test
25/09/2008 100% Completed with some
issues
• Activation all orders direct
to WA cust (ex 3pl)
12/10/2008 50% Completed Bunning’s only
•
Milestone Deliverables scheduled for completion over next period
Milestone Deliverables Due Date % Completed Deliverable Status
Milestone 1 Transition of stock into 3PL environment
• Activation of SCT 3pl 15/10/2008 0% Will deliver by new due
date
• Full stock return to melb 01/11/2008 20% Will be at 70% by EOP
•
Milestone 2 Warehouse & office closures
• IT Config Office/3pl 15/10/2008 50% pending
Confidential Page 5 2/4/2015
Project Status Report
• Lease transition to
Onesteel
15/10/2008 80% Pending expect a result
(Colliers)
•
Project impact of milestone success or failure for project remainder
1. Failure to deliver will result in
customer backlash
2. IT component will result in delivery
performance failures. Lease
transition failure will increase cost to
Nylex in rent recovery
Project Budget/Financial Status
Budget Item
Planned
Budget Actual Cost Variance/Explanation
Stock return to melb $60k Part completed N/A
Office rework $20k Not started N/A
Project Risk Management Status
Risk and Description
Risk
Chance
Risk
Impact
Risk
Priority Change from Last Review
• 3pl IT solution
• 3PL not ready &
does not ship
Low
Low
High
High
A1
A1
N/A (customer impact)
N/A (customer impact)
• Sub lease fails
• Provider service
failure (transport)
Low
Low
Medium
High
B1
A2
N/A (cost)
N/A (service impact during
changeover)
Project Issue Management Status
Issue and Description
Project
Impact
Target
Due Date
Issue
Status Issue Resolution
• Performance
reporting config
•
Low 15/10/2008 Pend
SCT to update report
•
•
Confidential Page 6 2/4/2015
Project Status Report
Project Recommendations
• R Egar to complete sub-lease agreement.
• SCT to complete performance reporting
•
•
•
•
Objectives for Next Project Status Review
Performance reporting to be completed for both SCT & Nylex. Sub lease to be signed off.
3pl solution to be active & running
PROJECT STATUS REPORT APPROVALS
Prepared by __________________________________
Project Manager
Approved by __________________________________
Fulfillment group manager
__________________________________
Sales group manager
Confidential Page 7 2/4/2015
Project Status Report
Confidential Page 8 2/4/2015

More Related Content

PDF
[系列活動] 智慧製造與生產線上的資料科學 (製造資料科學:從預測性思維到處方性決策)
PPT
2012人因工程改善輔導
PPT
現場改善與管理寶典
DOCX
Status report template
DOC
Agenda for Project Status Meeting
PPTX
Status report template
DOCX
Example Warehouse Monthly Report Template
DOCX
Project status report template v2.0
[系列活動] 智慧製造與生產線上的資料科學 (製造資料科學:從預測性思維到處方性決策)
2012人因工程改善輔導
現場改善與管理寶典
Status report template
Agenda for Project Status Meeting
Status report template
Example Warehouse Monthly Report Template
Project status report template v2.0

Similar to Wa warehouse project status report (20)

PPTX
Bayonne packaging final ppt
PPT
Blackbeltpresentation
PPTX
201601007 Limelight - Hui Qin Teoh
PPTX
The construction programme - assurance and controls
PPT
Lean Six Sigma Green Belt Certification 1
PDF
System Analysis and Design Project
PPTX
SAP for SCM OTIF Improvement Project-External
DOCX
Project Planning – Developing the Project Plan and Determining Cri.docx
PPTX
Antara Dashboard-002.pptx
DOCX
Arnel Moncada Resume
PPSX
Dada enterprise cost management solution comparisons
PPT
End User ServicesV1.0 training.ppt
PPT
Tollgate Presentation
PDF
Atos Worldline Project I Rui Zhu Telerex
PPTX
Presentación de avances para proyecto DISTRILUZ
PDF
Kick off meeting presentation
PDF
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journey
PPT
PUG2008 SCHR for Distribution
PPTX
Bluestream lavaconoct2015v1
PPTX
Liz's Bakery Master_kb0428
Bayonne packaging final ppt
Blackbeltpresentation
201601007 Limelight - Hui Qin Teoh
The construction programme - assurance and controls
Lean Six Sigma Green Belt Certification 1
System Analysis and Design Project
SAP for SCM OTIF Improvement Project-External
Project Planning – Developing the Project Plan and Determining Cri.docx
Antara Dashboard-002.pptx
Arnel Moncada Resume
Dada enterprise cost management solution comparisons
End User ServicesV1.0 training.ppt
Tollgate Presentation
Atos Worldline Project I Rui Zhu Telerex
Presentación de avances para proyecto DISTRILUZ
Kick off meeting presentation
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journey
PUG2008 SCHR for Distribution
Bluestream lavaconoct2015v1
Liz's Bakery Master_kb0428
Ad

More from Tom Evans (20)

PPT
NZ Distribution Changes
PDF
Trying to save Nylex...............Weeklyreporting 6 nov 2008
PDF
NYLEX CONSUMER PRODUCTS MATRIX JAN 05
PDF
SAP WMS install Somerton NYLEX_Operational_Support
PDF
Nylex Water Solutions Ingleburn - Main Body
PPT
RFP-Nylex-QLD-Version 1.3
PDF
Somerton Warehouse
PPT
West distribution changes
DOC
Wa warehouse project status report
DOC
P d national dist mngr
PDF
Packaged vehicle profile
PPT
Nz distribution changes
DOC
Nylex letterhead 08
DOC
Nylex consumer rfp
PPT
New nylex power piont pres
PPT
Fulfillment group oct 08
DOC
Delivery service offer user guide v1.0
DOC
~$Lex consumer rfp
DOC
Pg all sites period 4 f08
DOC
Nylex rfi international freight nylex
NZ Distribution Changes
Trying to save Nylex...............Weeklyreporting 6 nov 2008
NYLEX CONSUMER PRODUCTS MATRIX JAN 05
SAP WMS install Somerton NYLEX_Operational_Support
Nylex Water Solutions Ingleburn - Main Body
RFP-Nylex-QLD-Version 1.3
Somerton Warehouse
West distribution changes
Wa warehouse project status report
P d national dist mngr
Packaged vehicle profile
Nz distribution changes
Nylex letterhead 08
Nylex consumer rfp
New nylex power piont pres
Fulfillment group oct 08
Delivery service offer user guide v1.0
~$Lex consumer rfp
Pg all sites period 4 f08
Nylex rfi international freight nylex
Ad

Wa warehouse project status report

  • 1. Project Status Report Project Name: Consumer distribution changes Department: Fulfillment Focus Area: WA Warehouse Prepared By: Tom Evans Document Owner(s) Organization Role Dave Armstrong Fulfillment team Fiona Dickson Sales team Project Status Report Version Control Version Date Author Change Description 1.0 08/10/2008 Tom Evans Document created Confidential wawarehouseprojectstatusreport-150203194546-conversion-gate01.doc Last printed on 10/8/2008 22:08:00 a10/p10
  • 2. Project Status Report TABLE OF CONTENTS PROJECT STATUS REPORT PURPOSE.....................................................................................3 PROJECT STATUS REPORT .......................................................................................................3 1.1 Project Status Report Details.............................................................................................3 1.2 Project Status Report Template.........................................................................................3 PROJECT STATUS REPORT APPROVALS.................................................................................7 Confidential Page 2 2/4/2015
  • 3. Project Status Report PROJECT STATUS REPORT PURPOSE The Project Status Report document is a means of formal regular reporting on the status of a project to key project stakeholders, including senior management & the fulfillment / sales teams PROJECT STATUS REPORT 1.1 Project Status Report Details The project status report details will include the following data & comments & be broken up into the following categories. • Overall status & comments • Progress on 3PL transition • Carrier/provider performance to date • Warehouse sub-lease status • Sales office relocation • Staff morale • IT • Budget controls 1.2 Project Status Report Template Project Name: Consumer distribution changes Prepared By: Tom Evans Date: 08/10/2008 Reporting Period: 08/10/2008 to 15/10/2008 Project Overall Status: Project is overall on time. There have been some initial hiccups that have resulted in some delivery issues to store & other changes to the overall plan. None of these will result in the failure of the overall task - the strategic exit of the WA consumer warehouse. Confidential Page 3 2/4/2015
  • 4. Project Status Report Project Summary: Warehouse stock transition into 3PL • This was due this weekend but has been delayed by the provider due to unexpected stock take from another client. This will not delay the overall project. Freight direct to WA customers. 1. Some difficulty in this area was complicated by numerous factors. Some of which are Nylex driven example, the failure to label deliveries correctly. Some by the carrier’s performance due to breakdowns in the system. All aspects of this are being addressed. 2. Delivery reporting templates are being established to deliver detailed delivery reports inclusive of delivery dates to customer – see embedded sample. This has both details from Nylex & SCT systems Delivery & performance reporting Attached is a document consisting of 4 tabs relating to differing delivery status 1. “WA all Invoices” this relates to all deliveries invoice for WA in last month 2. Deliveries to WA that are in pick slip at Somerton 3. SCT delivery data including pickup times & delivery times. This is valid data & report is still a work in progress. 4. Nylex delivery data relating to the deliveries in the SCT report. WA Nylex SCT bunnings delivery data.xls **Please note SCT reporting is immature & will be available next week data in current report is live** Warehouse sub lease status • Colliers has worked closely with Nylex on the sob-lease option for the Nylex warehouse in Perth. Numerous meeting have been held with Onesteel & Nylex have prepared letters of offer to Onesteel with a start date of November 1st . A favorable result is forecasted Sales Office relocation • Geoff Radford is handling the sales office relocation. Assessment of works has been carried out & this relocation will not impact the project. Staff morale • Staff are coping well with the changes in the warehouse environment – no real issues to report Geoff Radford should speak to behalf of the office staff. Confidential Page 4 2/4/2015
  • 5. Project Status Report IT config • Some teething problems, though Martin C has all aspects well under control for both 3pl option & sales office config Budget Controls • Very little expenditure has occurred during these early stages. Costs included in attachment Milestone Deliverables performance reporting current period Milestone Deliverables Due Date % Completed Deliverable Status Milestone 1 : Data analysis & planning • A class items to 3pl analysis 12/10/08 100% Complete • Stock return to Melb 01/11/08 20% Pending • Warehouse sub lease 01/11/2008 80% Pending • Activation of 3pl 12/10/200 0% Pending /late (2 days) • Sale office relocation 01/11/2008 50% pending Milestone 2 Delivery testing ex Melbourne • Bunning’s only delivery test 25/09/2008 100% Completed with some issues • Activation all orders direct to WA cust (ex 3pl) 12/10/2008 50% Completed Bunning’s only • Milestone Deliverables scheduled for completion over next period Milestone Deliverables Due Date % Completed Deliverable Status Milestone 1 Transition of stock into 3PL environment • Activation of SCT 3pl 15/10/2008 0% Will deliver by new due date • Full stock return to melb 01/11/2008 20% Will be at 70% by EOP • Milestone 2 Warehouse & office closures • IT Config Office/3pl 15/10/2008 50% pending Confidential Page 5 2/4/2015
  • 6. Project Status Report • Lease transition to Onesteel 15/10/2008 80% Pending expect a result (Colliers) • Project impact of milestone success or failure for project remainder 1. Failure to deliver will result in customer backlash 2. IT component will result in delivery performance failures. Lease transition failure will increase cost to Nylex in rent recovery Project Budget/Financial Status Budget Item Planned Budget Actual Cost Variance/Explanation Stock return to melb $60k Part completed N/A Office rework $20k Not started N/A Project Risk Management Status Risk and Description Risk Chance Risk Impact Risk Priority Change from Last Review • 3pl IT solution • 3PL not ready & does not ship Low Low High High A1 A1 N/A (customer impact) N/A (customer impact) • Sub lease fails • Provider service failure (transport) Low Low Medium High B1 A2 N/A (cost) N/A (service impact during changeover) Project Issue Management Status Issue and Description Project Impact Target Due Date Issue Status Issue Resolution • Performance reporting config • Low 15/10/2008 Pend SCT to update report • • Confidential Page 6 2/4/2015
  • 7. Project Status Report Project Recommendations • R Egar to complete sub-lease agreement. • SCT to complete performance reporting • • • • Objectives for Next Project Status Review Performance reporting to be completed for both SCT & Nylex. Sub lease to be signed off. 3pl solution to be active & running PROJECT STATUS REPORT APPROVALS Prepared by __________________________________ Project Manager Approved by __________________________________ Fulfillment group manager __________________________________ Sales group manager Confidential Page 7 2/4/2015